  • Question 461:

    Which process is largely about preventing poorly conceived projects from ever being initiated?

    A. Starting Up a Project
    B. Initiating a Project
    C. Closing a Project
    D. Directing a Project

  • Question 462:

    A stakeholder wishing to make an observation about the project would do what?

    A. Ask for it to be included in the Communication Management Strategy
    B. Raise an issue
    C. Make an entry in the Issue Register
    D. Arrange a meeting with a Project Board member

  • Question 463:

    Which is a purpose of the Project Product Description?

    A. Define the key responsibilities for delivering product quality
    B. Provide information about the state of products
    C. Define the quality anticipated by the customer
    D. Provide product cost input tothe Business Case

  • Question 464:

    During the `managing a stage boundary' process, if external factors are identified that may affect the business justification for a project, which product should be updated?

    A. Business case
    B. Project brief
    C. End project report
    D. Highlight report

  • Question 465:

    Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

    A. controls
    B. products
    C. project management team
    D. stages

  • Question 466:

    The Business Case describes the reasons for undertaking the project based on estimated costs, the major risks and what else?

    A. Approach to deliver the chosen business solution
    B. Measurable acceptance criteria
    C. Project's products to be produced
    D. Expected business benefits

  • Question 467:

    Which plan provides the Business Case with costs during the Initiating a Project process?

    A. Initiation Stage Plan
    B. Project Plan
    C. Stage Plan
    D. Team Plan

  • Question 468:

    What is a purpose of a Lessons Log?

    A. Document and maintain information on issues
    B. Note who should be sent copies of a Highlight Report
    C. Note information from other projects which could be input to the project's strategies and plans
    D. Document the results of quality checking activities

  • Question 469:

    Which is a purpose of the change budget?

    A. To fund the costs introduced be new requests for change
    B. To fund the increased cost of planned work that exceeds tolerance
    C. To ensure implementation of changes is streamlined
    D. To fund the work to deliver the products to the defined quality criteria

  • Question 470:

    Which is an objective of the Closing a Project process?

    A. Review and approve the plan for project closure
    B. Review the performance of the project against its baseline
    C. Perform any post-project reviews
    D. Create a Benefits Review Plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.