  • Question 481:

    How is the tailoring approach defined for a project?

    A. The project board approves the approach
    B. The project board documents the approach
    C. Project assurance approves the approach
    D. Project assurance documents the approach

  • Question 482:

    Which product would be updated to show that a decision has been made on an off-specification which has now been closed?

    A. Quality Register
    B. Daily Log
    C. Issue Report
    D. Risk Register

  • Question 483:

    Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

    A. Checkpoint Report
    B. End Stage Report
    C. End Project Report
    D. Product Status Account

  • Question 484:

    Which of the following are typical activities of a configuration management procedure?

    1.

    Impact assessment

    2.

    Control

    3.

    Verification and audit

    4.

    Status accounting

    A. 1,2,3
    B. 1,2,4
    C. 1,3,4
    D. 2,3,4

  • Question 485:

    Which factor should influence the structuring of the project into management stages?

    A. The amount of risk within the project
    B. The availability of the project board
    C. The number of recorded requests for change
    D. The quality process of the organization

  • Question 486:

    Which is a purpose of a Daily Log?

    A. Record the products and activities planned for the stage
    B. Record informal issues
    C. Record and track the status of all products produced during a stage
    D. Update the Project Board on the progress of a stage

  • Question 487:

    A principle of PRINCE2 is that every project must have which one of the following?

    A. Defined and agreed roles and responsibilities with an organization structure that engages the business, user and supplier primary stakeholder interests
    B. People allocated to clearly defined management jobs, assigned to them on a one-to-one basis
    C. As many stakeholders as possible from the customer environment involved in key decision- making throughout the project life cycle
    D. Stakeholders who are responsible, accountable, consulted and informed throughout every stage of the project

  • Question 488:

    Which should be used to document any uncompleted work that needs to be done, and any risks which need to be managed after the project has closed?

    A. Follow-on action recommendations
    B. Exception Report
    C. Issue Register
    D. Risk Register

  • Question 489:

    Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

    A. Change
    B. Cross-functional
    C. Unique
    D. Risk

  • Question 490:

    Who is the key project decision-maker in the project management team?

    A. Corporate management
    B. Executive
    C. Change Authority
    D. Project Manager

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.