A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?
A. Determine potential threats regarding compliance with the regulations.A project to develop a new service is initiated by a telecommunications operator. The project management plan has been developed, approved, and shared with the respective stakeholders.
What should the project manager do next?
A. Define deliverables, activities, and scheduling information.An organizational policy requires project managers to carry out two audits per month: one for their own project and one for another project manager's project. After a recent audit review, team members suggested that it is not fair to have their deliverables audited by a peer.
What should the project manager do to avoid this situation?
A. Ask the organization to remind staff that audits are a requirement.A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed.
What should the project manager do to deliver business value to the client?
A. Request to use the management reserve and crash the project schedule.In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager found out that the delay is due to the developer's lack of understanding of the customer requirements shared by the off-site team.
What should the project manager do?
A. Replace the developer with a skilled resource.A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and delay new feature development. Which action should the project manager take to resolve the quality issues?
A. Plan for continuous validation of the product.Due to a recent company merger, a project manager from company B has been assigned to a team composed of team members from company A. At the start of the project, conflicts arise due to a lack of clarity on processes and the project manager's relationship with company B.
What should the project manager do to resolve this conflict?
A. Avoid the conflict, as the customer is comfortable using company A's processes.A project for Company A was successfully delivered within scope, schedule, and budget by the end of the last iteration. However, during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.
What should the project manager have done to avoid this perception?
A. Involved the business stakeholders in the sprint reviewA new sales software development project is underway. The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.
Which project approach should the project manager take?
A. IncrementalDuring a project's third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip. What should the project manager do?
A. Guide the team to revert back to the forming and storming stagesNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.