During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task. What should the project manager do?
A. Ask the new team member to follow the team ground rules.A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After 3 days of work, the project manager completed two actions and spent US$80,000.
What should the project manager do next?
A. As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus. Which conflict resolution approach did the project manager use?
A. CompromiseA project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?
A. Tell the supplier that they have an obligation to supply the raw material.In a multinational multi location project with virtual teams a project manager has established a project baseline. The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.
What should the project manager calculate to address this critical budgetary situation? (Choose two)
A. Contingency control in the project and rebaselineThe project manager just started leading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule.
What should the project manager do?
A. Conduct a meeting with the project team to discuss and address the sources of disagreementA project manager has expertise in the technical domain. The project manager frequently demonstrates unacceptable behavior toward other team members; however, when confronted, the project manager denies this behavior. What is the reason for the project manager's behavior?
A. The project manager lacks necessary empathy.A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?
A. Rebaseline the project schedule to absorb the delay.A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.
What should the project manager do?
A. Recommend to the PMO that it is not the right time to start implementing new tools for projects.An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
A. Establish a team charter.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.