A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?
A. Communicate the risk to the steering committee and request a mitigation plan from senior management.A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week. What should the project manager do next?
A. Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform for another year at a higher support price.
What should the product owner do about this situation?
A. Reprioritize the backlog based on value and cost of delay divided by duration.A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing. What should the project manager do to create a positive environment?
A. Establish the team ground rules and share them with the team for strict adherence.A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became concerned that the product quality will be sacrificed. What should the project manager do?
A. Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process.
What should the project manager do?
A. Descope low-priority features that were not explicitly requested and add this feature as a high priority.A project manager found a repeated defect in a junior developer's code. The code is due in 2 days and a severe fine will be incurred if it is not fixed by then. The project manager wants to reassign the assignment to a more senior developer, but the junior developer is strongly opposed to the reassignment.
What should the project manager do?
A. Assign the issue to a senior developer and schedule training for the junior developer after the due date.A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.
What should project manager do?
A. Seek management's approval for executing the contract earlier than planned.A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?
A. Ensure that the project issue log is up-to-date with the customer's issues related to the missed stories.A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor's feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.
How should the project manager mitigate this situation?
A. Execute a retrospective meeting to solve the misalignment.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.