Exam Details

  • Exam Code
    :PMI-PBA
  • Exam Name
    :PMI Professional in Business Analysis
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :200 Q&As
  • Last Updated
    :May 12, 2024

PMI PMI Certifications PMI-PBA Questions & Answers

  • Question 11:

    A project team has completed the system use cases along with accompanying screen mockups. The business analyst schedules a review meeting with the client team to walk through the artifacts.

    What is the purpose of this meeting?

    A. To validate that the system is aligned with the stakeholder requirements

    B. To verify that the documents are aligned with the transition requirements

    C. To validate that the documents are aligned with the solution requirements

    D. To verify that the system is aligned with the quality requirements

  • Question 12:

    A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a

    business need.

    Which type of requirements are these?

    A. Tested

    B. Out-of-scope

    C. Implemented

    D. In-scope

  • Question 13:

    A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.

    Which metrics tool should the business analyst use to record the results?

    A. Focus group

    B. Business completion

    C. Sales and marketing

    D. Customer

  • Question 14:

    Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s) versioning?

    A. Project plan

    B. Statement of work

    C. Traceability matrix

    D. Problem or opportunity statement

  • Question 15:

    In the first few weeks after a large implementation of a new web-based application, a critical report failed. Further investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.

    Which technique could have prevented this problem from occurring?

    A. Prototyping

    B. Use cases

    C. Document analysis

    D. Diagrams

  • Question 16:

    A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

    A. Prototyping

    B. Stakeholder analysis

    C. Group decision making

    D. Questionnaires

  • Question 17:

    A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.

    What could have caused the documentation to be returned?

    A. The analyst did not include the scope document in the acceptance criteria paperwork.

    B. The analyst utilized user stories as a requirements document tool.

    C. The analyst failed to gather any baseline information.

    D. The analyst performed forward and backwards traceability.

  • Question 18:

    A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.

    Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that those issues are resolved?

    A. Interviews

    B. Problem tracking

    C. Process modeling

    D. Estimation

  • Question 19:

    For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?

    A. Interface analysis

    B. Risk analysis

    C. System analysis

    D. Dependency analysis

  • Question 20:

    The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.

    Which technique should the business analyst have followed to ensure consensus?

    A. The business analyst should have invited the key stakeholders to the meeting.

    B. The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.

    C. The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.

    D. The business analyst should have performed a complete review of each requirement with one of the stakeholders' peers before the meeting.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-PBA exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.