Which tool is the most appropriate to aid in development of measurable and actionable requirements for a new project?
A. Entity relationship diagram
B. Network diagram
C. Activity-on-node diagram
D. Use case diagram
What can a business analyst use to track requirements documentation?
A. Business rules matrix
B. Version control system
C. Data dictionary
D. Affinity diagram
The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?
A. Create a requirements traceability matrix for review and approval by the customer.
B. Create a requirements baseline approval form for the customer to review and approve.
C. Request that the customer create a baseline of the requirements in the contract specification.
D. Perform a variance analysis on the design specification and report the results to the customer.
When modeling processes or analyzing tasks, business rules can be uncovered by asking about:
A. work that may be performed out of sequence.
B. reasons for choosing a particular course of action.
C. tasks that overlap with each other.
D. task transitions that hinder organizational performance.
The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders' views conflict.
Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?
A. Decision trees, weighted matrix, and context diagrams.
B. Traceability matrix, context diagrams, and scope document.
C. Weighted matrix, process flow, and organizational chart
D. Stakeholder register, decision tree, and capability matrix
A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems.
Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?
A. Rules modeling
B. Enterprise modeling
C. Interface modeling
D. Data modeling
When eliciting requirements, a good time to consider using the interviewing method is when:
A. attempting to obtain sign-off on requirements form stakeholders.
B. there are communication challenges among stakeholders.
C. assembling a requirements traceability matrix.
D. there is not enough time to gather requirements from many different sources.
A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?
A. Business case
B. Project charter
C. Survey
D. Storyboard
A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.
From the business analysis perspective, the main reason for this business failure was a failure to:
A. establish measurable success criteria in the business case.
B. gather the appropriate usability requirements.
C. set the product positioning.
D. review and evaluate market expectations.
Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:
A. prepare a test procedure for the product to discuss at the requirements review.
B. start designing the product to impress the customer with the amount of progress achieved early in the project.
C. evaluate the requirements and highlight those that cannot be met or need to be deferred.
D. request a contract amendment to delete any requirements from the contract that will be difficult to meet.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-PBA exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.