CompTIA PK0-005 Online Questions & Answers

  • Question 501:

    Which of the following would be the most helpful in providing customers with an application accessible via a web browser?

    A. IaaS
    B. SaaS
    C. PaaS
    D. XaaS

  • Question 502:

    After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the

    project manager realizes the candidate has a non-compete agreement from the previous employer.

    Which of the following should the project manager do?

    A. Withdraw the offer to the candidate and raise this as a risk.
    B. Ignore a potential lawsuit since this is a critical project.
    C. Use a third-party company for the contract to legally avoid responsibility.
    D. Have a meeting with the project sponsor to discuss the situation.

  • Question 503:

    After a project's completion, the project manager and the executive leadership team decide to reward the team.

    Which of the following documents should the PM and the executive leadership team review before determining rewards?

    A. Statement of work
    B. Rules of engagement
    C. Project scope statement
    D. Organizational ethics policy

  • Question 504:

    A team has just finished a major stage of a project. The project manager now has to evaluate the work completed up to this point, what tasks still need to be completed, and reassess risks and scope.

    Which of the following best describes what the project manager should perform?

    A. Gap analysis
    B. Work breakdown structure
    C. External status report
    D. Phase gate review

  • Question 505:

    A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

    A. Provide end-user training.
    B. Decommission old systems.
    C. Release external consultants.
    D. Monitor performance.

  • Question 506:

    Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

    A. SaaS
    B. IaaS
    C. DaaS
    D. PaaS

  • Question 507:

    A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

    A. Perform a gap analysis.
    B. Escalate the issue.
    C. Submit a change request.
    D. Approve deliverables.

  • Question 508:

    As a result of an unpredicted risk, a project manager is documenting a request in the change control log.

    Which of the following change control processes should the project manager do last?

    A. Escalate to the change control board.
    B. Update the project plan.
    C. Test the implemented change request.
    D. Communicate the change deployment.

  • Question 509:

    A project manager created an NDA document for the project team to sign due to the sensitivity of private data loaded in the production environment.

    Which of the following data types is the project manager most likely securing?

    A. Restricted
    B. Personally identifiable information
    C. Confidential
    D. Internal

  • Question 510:

    A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

    A. SOW
    B. RFI
    C. RFQ
    D. WBS

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.