CompTIA PK0-005 Online Questions & Answers

  • Question 521:

    A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

    A. Start-to-finish
    B. Finish-to-finish
    C. Finish-to-start
    D. Start-to-start

  • Question 522:

    A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

    A. Assign a scribe to take notes.
    B. Record the meeting and transcribe the notes later.
    C. Instruct each team member to take notes.
    D. Get a facilitator for the meetings.

  • Question 523:

    A new project at a company went live, which led to a data breach of client medical records. Which of the following best describes what was leaked?

    A. User acceptance information
    B. Personally identifiable information
    C. Payment card information
    D. Personal health information

  • Question 524:

    Which of the following best represents the project impact to a company's brand value?

    A. The project is compliant with local and state laws and becomes the standard for new projects.
    B. The project promotes new initiatives to expand its benefit to other communities.
    C. The project exceeds the sales quota for the third quarter and raises the bar for next periods.
    D. The project meets the expected milestones and finishes on time and within budget.

  • Question 525:

    Which of the following describes some of the features of the Agile methodology?

    A. It uses a direct approach, Gantt charts, and a ticketing system.
    B. It uses an indirect approach, spreadsheets for documentation, and change request documents.
    C. It uses an iterative approach, backlogs, and burndown charts.
    D. It uses a step-by approach, an issue log, and pie charts.

  • Question 526:

    Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

    A. RFI
    B. RFP
    C. RFQ
    D. RFB

  • Question 527:

    A project manager wants to review the deliverables outsourced in a project. Which of the following should the project manager use? (Choose two.)

    A. TOR
    B. SOW
    C. MOU
    D. RFP
    E. NDA
    F. WBS

  • Question 528:

    A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio.

    Which of the following should the manager use to accomplish this task?

    A. Dashboard
    B. Status report
    C. Gantt chart
    D. Email

  • Question 529:

    While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM

    knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project.

    Which of the following should the PM do FIRST?

    A. Escalate the finding to the change control board.
    B. Add a risk to the risk register for validation.
    C. Consult the RACI matrix to identify ownership of the risk.
    D. Have a meeting with the project sponsor and main stakeholders.

  • Question 530:

    A project manager needs to prepare for the project kickoff during the initiation phase. Which of the following activities should be conducted?

    A. Establishing accepted communication channels
    B. Developing the records management plan
    C. Reviewing existing artifacts
    D. Assessing stakeholders

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.