  • Question 211:

    A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

    A. Scatter diagram
    B. Decision tree
    C. Pareto chart
    D. Histogram

  • Question 212:

    The project manager must create a project charter.

    Which of the following should be included in the charter?

    A. Project schedule
    B. Resource allocation
    C. Risk plan
    D. Stakeholder identification

  • Question 213:

    Which of the following best describes the difference between the current state and the desired future state in project management?

    A. The current state is a high-level view of the project scope, and the desired state is what is happening right now.
    B. The current state is where the business is now, and the desired state is where the project is going to take the business.
    C. The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.
    D. The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

  • Question 214:

    A utility company issued a directive stating that projects impacting operating systems will not be executed during hurricane season. Which of the following is being acknowledged by this directive?

    A. Company brand value
    B. National environments
    C. Standard operating procedures
    D. Local emergency policies

  • Question 215:

    A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

    A. Forming, storming, performing, norming, adjourning
    B. Forming, performing, storming, norming, adjourning
    C. Forming, norming, storming, performing, adjourning
    D. Forming, storming, norming, performing, adjourning

  • Question 216:

    Which of the following is a Kanban concept?

    A. Ensuring business alignment by development iteration
    B. Representing cost-effective tasks through different colors
    C. Allocating resources to high-priority tasks
    D. Managing flow by limiting work in progress

  • Question 217:

    A project manager needs to pull data from a burndown chart. Which of the following should the project manager analyze to obtain this data in the most efficient way?

    A. Number of people available
    B. Remaining and completed tasks
    C. Cost variance
    D. Number of issues registered

  • Question 218:

    During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

    A. negotiating resources.
    B. assigning resources.
    C. assessing the resource pool.
    D. adding resources to the schedule.

  • Question 219:

    A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

    A. Responsibility assignment matrix
    B. Acceptable communication channels
    C. Risk registry
    D. Staff directory

  • Question 220:

    A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

    A. Validate against the scope statement and ask for sign-off.
    B. Run a control chart to ensure the quality of the deliverables.
    C. Review the risk register and close up residual risks.
    D. Start the training and handoff for the operations team.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.