  • Question 221:

    When looking for solutions, which of the following procurement documents should be used?

    A. CDM
    B. CCM
    C. RFI
    D. RFQ

  • Question 222:

    After which of the following documents is signed off by stakeholders can a project begin?

    A. Project stakeholder requirements
    B. Project charter
    C. Project scope
    D. Project schedule

  • Question 223:

    Which of the following project documents lists risks and describes the strategy to deal with a risk?

    A. Risk categorization
    B. Risk register
    C. Risk analysis
    D. Risk breakdown structure

  • Question 224:

    Which of the following is a component of a risk management plan?

    A. RAM
    B. RBS
    C. COQ
    D. KPI

  • Question 225:

    Which of the following individuals BEST represents the authority to authorize changes to the triple constraints?

    A. Functional manager
    B. Sponsor
    C. Team member
    D. Project manager

  • Question 226:

    Which of the following represents a good reason for formally closing out a project?

    A. To provide historical information for future projects
    B. To manage stakeholders' expectations
    C. To promote team cohesiveness
    D. To keep a record in case someone comes back later with an issue after transition

  • Question 227:

    A project is struggling because the sponsor continually has to increase funding which may cause the project to get cancelled. This could have been avoided by using:

    A. Quality metrics.
    B. Change control.
    C. A WBS.
    D. Fixed costs.

  • Question 228:

    Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account. Which of the following should the project manager do to ensure stakeholder expectations are met?

    A. Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps
    B. Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks
    C. Escalate the issue to the project steering committee that Ann is criticizing the project quality
    D. Organize a requirements workshop to capture any gaps

  • Question 229:

    Which of the following regarding project documentation can be found in organizational governance documents? (Select TWO).

    A. Length of time project documents must be kept
    B. Rules regarding the usage of documentation version numbers
    C. Issue management procedures
    D. Asset management documentation
    E. Team member contact information

  • Question 230:

    When dealing with remote project team members, it is important to recognize their needs in terms of which of the following? (Select TWO).

    A. Time zone differences
    B. Programming language differences
    C. Cultural differences
    D. Project management differences
    E. Compensation differences

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.