  • Question 311:

    The program manager takes over a poorly performing program. After a review of the documentation and interviews with the program sponsor, stakeholders, and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent projects and components to meet the program's needs.

    What action should the program manager take to realign the program?

    A. Assess the program schedule and determine how to maintain all projects and components within the program.
    B. Discuss the situation with the program stakeholders and let them decide which projects to accelerate and which to close.
    C. Discuss the situation with the program sponsor(s) and let the sponsor(s) make the decision as to which projects to accelerate and which to close.
    D. Develop a change request to present to the governance board, accelerate some projects, close some projects, and reassign some resources.

  • Question 312:

    A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment, and is intolerant of processes to the point of being considered process-adverse. However, the company's culture is tolerant of long-term program activities, provided there is continuous progress on improving the protection of its intellectual property. Expectations for rapid progress are low.

    What should the program manager do next?

    A. Tailor program sponsor and stakeholder engagement and communications activities to meet the company's expectations
    B. Insist on maintaining a set of tightly controlled stakeholder register and engagement plan documents to meet expectations
    C. Provide detailed information to the most influential program sponsors and stakeholders
    D. Ensure that the component stakeholders have the appropriate level of communications required to meet their needs

  • Question 313:

    Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance. To resolve this situation, which of the following must go through critical review and change?

    A. Program Benefits Management domain
    B. Stakeholder communications requirements
    C. Program communications report
    D. Program communications management plan

  • Question 314:

    You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders' concerns, threats, and demands for communication. They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?

    A. RACI chart
    B. Stakeholder analysis chart
    C. Roles and responsibilities chart
    D. Communication matrix

  • Question 315:

    Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

    A. Resource breakdown structure
    B. Resource management chart
    C. Stakeholder analysis chart
    D. RACI chart

  • Question 316:

    You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

    A. Contract and the quality measurements for the vendor's work
    B. The scope verification document and the termination notice
    C. Contract and scope verification process documents
    D. Work that has been completed and uncompleted work

  • Question 317:

    Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

    A. RFI
    B. RFP
    C. RFQ
    D. IFB

  • Question 318:

    You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

    A. Programs always cost less than multiple projects in an organization.
    B. Project management is centralized to the program manager.
    C. Programs provide centralized risk management.
    D. Program management makes communication easier among the project managers and project team.

  • Question 319:

    A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

    A. Schedule, because the program's planned value is only $700,000.
    B. Cost, because the program has a cost variance of -7,500
    C. Schedule, because the program has a schedule performance index of .88.
    D. Cost, because the program has an estimate to complete of $1,151,429.

  • Question 320:

    You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

    A. Avoidance
    B. Mitigation
    C. Transference
    D. Enhancing

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PGMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.