Skip to main content

PGMP Real Exam Questions

Program Management Professional (PgMP)

452 questions available · Page 1 of 46

Updated Exam DumpsVerified AnswersPass Guarantee

Get Complete Exam Dumps
Question 1 Single choice

A regional finance program is impacted by a new currency regulation issued by a country in the region.
The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year. Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation, as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured.

What should the program manager do to address the risk?

  1. A

    Build a coalition with local companies that can influence the government to renegotiate the imposed deadline.

  2. B

    Create fine and closure scenarios to assess the impact on the program and create a contingency plan.

  3. C

    Generate a delivery incentive contract with the selected fiscal expert to ensure on-time delivery of the revised financial statements.

  4. D

    Assess the risk, incorporate it in the program's risk management plan, and meet with the steering committee.

Show answer and explanation

Correct answer: B

Question 2 Single choice

Paul is the program manager for his company. He along with his team is working on the Monitor and Control Program Changes process. The process will need several inputs.

Which one of the following items is NOT an input to the Monitor and Control Program Changes process in the program management?

  1. A

    Change request log

  2. B

    Approved change requests

  3. C

    Change requests

  4. D

    Program management plan

Show answer and explanation

Correct answer: B

Question 3 Single choice

You are coaching Tammy, a project manager in your program, on the benefits of program management.
She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program.

Which one of the following is a benefit of creating a program?

  1. A

    Programs always cost less than multiple projects in an organization.

  2. B

    Project management is centralized to the program manager.

  3. C

    Programs provide centralized risk management.

  4. D

    Program management makes communication easier among the project managers and project team.

Show answer and explanation

Correct answer: C

Question 4 Single choice

You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work.
The outsourcing of the dangerous work to a specialist is what type of risk response?

  1. A

    Avoidance

  2. B

    Mitigation

  3. C

    Transference

  4. D

    Enhancing

Show answer and explanation

Correct answer: C

Question 5 Single choice

Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

  1. A

    Program charter

  2. B

    Program risk register

  3. C

    Program issue register

  4. D

    Program scope statement

Show answer and explanation

Correct answer: C

Question 6 Single choice

A program manager learns that their company's organizational strategy has changed. This change impacts one component project of a program, misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete.

What should the program manager do next?

  1. A

    Immediately submit a component project closure request to the program sponsor so that resources can be reallocated to strategically aligned component projects.

  2. B

    Assess the impact of closure on other component projects, and generate a recommendation for submission to the program governance board.

  3. C

    Recommend that the component project manager complete work activity to deliver benefits to the organization.

  4. D

    Update the benefits management plan to reflect the impact of the change on the program and its intended benefits.

Show answer and explanation

Correct answer: B

Question 7 Single choice

A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date.
Based on this information what is the cost performance index (CPI) for this program?

  1. A

    .93

  2. B

    .82

  3. C

    $323,889

  4. D

    -$38,889

Show answer and explanation

Correct answer: A

Question 8 Single choice

Which of the following shows the ratio between a task's budgeted and actual costs?

  1. A

    To-Complete Performance Index (TCPI)

  2. B

    Schedule Variance (SV)

  3. C

    Schedule Performance Index (SPI)

  4. D

    Cost Performance Index (CPI)

Show answer and explanation

Correct answer: D

Question 9 Single choice

You are the program manager for the NHQ Program. Your program has a budget of $4,500,000 and has lasted for two years. Your program has just completed its final deliverable and you're completing the final program closure processes.

What document must the program customer must now sign as part of program closure?

  1. A

    The customer must now sign the program scope.

  2. B

    The customer must now sign the payment for the program work.

  3. C

    The customer must now sign the certificate of program closure.

  4. D

    The customer must now sign the operational transfer agreement.

Show answer and explanation

Correct answer: C

Question 10 Single choice

After an organization initiates a strategic program, several project managers express interest in joining the program team. The program manager's supervisor recommends a list of project managers to be part of the team.

What should the program manager do to select the project managers?

  1. A

    Complete a skill set inventory and select the most suitable resource(s)

  2. B

    Ask interested project managers for their CV and conduct interviews

  3. C

    Accept the recommendation of the program manager's supervisor

  4. D

    Contact the human resource manager for project managers' availability

Show answer and explanation

Correct answer: A