JK0-017 Exam Details

  • Exam Code
    :JK0-017
  • Exam Name
    :CompTIA E2C Project+
  • Certification
    :CompTIA Certifications
  • Vendor
    :CompTIA
  • Total Questions
    :402 Q&As
  • Last Updated
    :Jul 12, 2026

CompTIA JK0-017 Online Questions & Answers

  • Question 341:

    During execution, a project manager of a construction project requires certain project team members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk of injury to those team members, without affecting the approved project schedule?

    A. Ensure that project team members do not work in very windy weather.
    B. Ensure that project team members are furnished with slip-resistant boots.
    C. Ensure that project team members are trained in injury response.
    D. Ensure that project team members are covered by applicable insurance.

  • Question 342:

    Given the following information: Pessimistic estimate is 30 days Most Likely estimate is 15 days Optimistic estimate is 10 days Which of the following is the expected duration for this scheduled activity?

    A. 11 days
    B. 17 days
    C. 25 days
    D. 29 days

  • Question 343:

    The project manager has the MOST authority in which of the following organizational structures?

    A. Balanced Matrix
    B. Functional
    C. Weak Matrix
    D. Strong Matrix

  • Question 344:

    A project manager receives formal leadership authority from which of the following documents?

    A. Resource matrix
    B. Project charter
    C. Work Breakdown Structure (WBS)
    D. Statement of Work (SOW)

  • Question 345:

    During which of the following process groups is the availability of required resources for the project determined?

    A. Executing
    B. Monitoring/Controlling
    C. Initiating
    D. Planning

  • Question 346:

    In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?

    A. $150,000
    B. $300,000
    C. $450,000
    D. $600,000

  • Question 347:

    Which of the following is a quantitative risk analysis tool or technique?

    A. Risk register
    B. Decision tree analysis
    C. Probability and impact matrix
    D. Cause and effect diagram

  • Question 348:

    Which of the following is the BEST communication option for team building?

    A. Send an email transmission to introduce the project.
    B. Send a completed project charter to introduce the project.
    C. Leave a voicemail message to introduce the project.
    D. Schedule a face-to-face meeting to introduce the project.

  • Question 349:

    An ongoing project requires several parts manufactured at an outside vendor. If the vendor has sufficient quantity and can still ship today, the parts should be received in five days; although in most cases an order of this size requires ten days. Allowing for an upcoming holiday and some potential bad weather the shipment could take up to twenty-one days. Using the PERT method, which of the following is the correct time estimate for a parts delivery?

    A. 10 days
    B. 11 days
    C. 21 days
    D. 36 days

  • Question 350:

    The lessons-learned activity and formal acceptance documentation form part of which of the following process groups?

    A. Closing
    B. Planning
    C. Executing
    D. Monitoring/Controlling

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.