JK0-017 Exam Details

  • Exam Code
    :JK0-017
  • Exam Name
    :CompTIA E2C Project+
  • Certification
    :CompTIA Certifications
  • Vendor
    :CompTIA
  • Total Questions
    :402 Q&As
  • Last Updated
    :Jul 12, 2026

CompTIA JK0-017 Online Questions & Answers

  • Question 241:

    Which of the following activity sequencing methods describes the start-to-start dependency?

    A. The completion of the successor activity depends upon the beginning of the predecessor activity.
    B. The completion of the successor activity depends upon the completion of the predecessor activity.
    C. The beginning of the successor activity depends upon the completion of the predecessor activity.
    D. The beginning of the successor activity depends upon the beginning of the predecessor activity.

  • Question 242:

    Which of the following are examples of a good business case for a new project? (Select Two).

    A. Increased profit opportunity for the customer
    B. Increased billing through maintenance contract
    C. Increased efficiency internally for the customer
    D. Increased engagement length with the customer
    E. Increased billing opportunity for the project team

  • Question 243:

    The project manager has documented a change request from a key project stakeholder. Which of the following actions should the project manager take NEXT?

    A. Discuss this change during the next status meeting.
    B. Ask other stakeholders for recommendations.
    C. Send the request to the change control board.
    D. Perform an impact analysis.

  • Question 244:

    Quality assurance is performed during which phase of a project?

    A. During the controlling phase
    B. During both controlling and execution phase
    C. During the execution phase
    D. During the planning phase

  • Question 245:

    A project manager has finished the first phase of a project. Who of the following determines if the project continues?

    A. End users
    B. Project manager
    C. Project team
    D. Project sponsor

  • Question 246:

    The initiation process concludes with the creation of which of the following?

    A. Contingency reserve
    B. Project charter
    C. Project schedule
    D. Project scope statement

  • Question 247:

    A project manager is managing the delivery of a project awarded under a fixed-cost contract. The project cost was poorly planned and underestimated, but the projects overall scope and deadline cannot change. Failure to deliver the project is not an option. Which of the following will MOST likely be affected by these circumstances?

    A. Earned Value (EV)
    B. Quality
    C. Change management
    D. Resource leveling

  • Question 248:

    Three of the team members are having a conflict with each other. Which of the following steps should the project manager take to minimize the conflict?

    A. Resolve the conflict by terminating the team members.
    B. Ignore the conflict and keep working on the project.
    C. Encourage the team members to resolve the conflict.
    D. Ask the project sponsor to resolve the conflict.

  • Question 249:

    Paperwork related to the project is not being signed in the correct order. The BEST way to correct this problem would be to implement a procedure for managing:

    A. required forms.
    B. document routing.
    C. change.
    D. document version control.

  • Question 250:

    Which of the following documents would be generated to solicit bids from outside vendors?

    A. WBS
    B. PERT
    C. RFP
    D. SOW

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.