CompTIA JK0-017 Online Questions & Answers

  • Question 151:

    The project is running behind schedule because one of the developers has taken an unscheduled vacation. The project manager informs the developer that any further unauthorized absence will result in removal from the project. Which of the following resolution techniques was used?

    A. Forcing
    B. Negotiating
    C. Avoiding
    D. Confronting

  • Question 152:

    The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?

    A. Obtain additional approval from the project sponsor.
    B. Discuss this change during the next status meeting.
    C. Perform a probability and impact analysis on the change.
    D. Create a plan to implement the change.

  • Question 153:

    Which of the following shows a project that is presently over its financial budget?

    A. CPI = 1.4
    B. CPI = 0
    C. CV = +$11,000
    D. CPI = 0.8

  • Question 154:

    In pre-project setup, which of the following must be completed prior to validating a project?

    A. Project definition
    B. Preliminary SOW
    C. Project charter
    D. Stakeholder approval

  • Question 155:

    Which of the following are common causes of project team conflict? (Select Two).

    A. Project schedule
    B. Competing resource demands
    C. Project budget
    D. Varying work styles
    E. Time zone differences

  • Question 156:

    Which of the following sequences represents the correct order for implementing a change request?

    A. Change is requested, change impact analyzed, change request submitted to board, change request approved, change implemented.
    B. Change is requested, change implemented, change impact analyzed, change request submitted to board, change request approved.
    C. Change is requested, change request submitted to board, change impact analyzed, change request approved, change implemented.
    D. Change is requested, change request submitted to board, change request approved, change implemented, change impact analyzed.

  • Question 157:

    If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

    A. -$1,000
    B. $1,000
    C. -$3,000
    D. $3,000
    E. There would be a 25 percent cost decrease.
    F. There would be a 75 percent cost increase.
    G. The project is over-budget.
    H. The project is under-budget.

  • Question 158:

    A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cannot possibly finish in less than 24 months. Which of the following tools can the project manager use to show the improbability of the proposed timeline?

    A. Pareto Diagram
    B. Decision tree
    C. Monte Carlo analysis
    D. Quantitative risk analysis

  • Question 159:

    Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the following should the shared resource be documented?

    A. Quality management metrics
    B. Work Breakdown Schedule (WBS)
    C. Scope statement
    D. Risk register

  • Question 160:

    The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:

    A. parametric estimating.
    B. bottom-up estimating.
    C. expert judgment.
    D. analogous estimating.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.