  • Question 161:

    System testing on your current project is coming to an end and it is time to write the test completion report. The product is an in-house development to support the Sales and Marketing department. Test design was based on requirements

    analysis.

    Which of the following metrics is MOST likely to be useful to help the business stakeholders decide if testing has met its objectives?

    A. Breakdown by risk level of coverage of product risks
    B. Breakdown by coverage type of the code coverage achieved
    C. Percentage of test cases that have been automated
    D. Breakdown by priority of coverage of requirements

  • Question 162:

    At what testing level do the test management activities Include coordinating with end users?

    A. Component testing
    B. Component Integration testing
    C. System testing
    D. Acceptance testing

  • Question 163:

    Test results are reported as "Requirements tested, passed, and failed". What test strategy are you using? [1]

    A. Model-based
    B. Exploratory
    C. Analytical
    D. Reactive

  • Question 164:

    You are the Test Manager for a critical system and are using a risk-based approach for this project. Which of the following would most clearly convey the current status to project stakeholders? [3]

    A. A scatter chart showing test execution status
    B. A Pareto graph showing requirements coverage
    C. A pie chart showing residual risk
    D. A bar graph showing defect density

  • Question 165:

    Your application development team is performing "test-driven" development. This is a core principal of which software development model? [1]

    A. Sequential
    B. Iterative
    C. Agile
    D. Spiral

  • Question 166:

    You are the Test Manager of a four-person test team working for a small distribution company with a single warehouse. Your team has been working with a third party development team on a new inventory management system. The company

    expects this system to generate approximately one million dollars per annum in profits for the company. Early in the project, various risks were

    identified, and steps taken to mitigate those risks.

    For example, you sent your test team for training on the new system, and upgraded the test environment.

    There are still some lingering risks that have not been addressed, but they have been determined to have a low chance of occurring, with minimal impact if they do occur.

    What would be the best option to mitigate these remaining risks? [3]

    A. Note the risks, and ignore them for now.
    B. Redo the project test plan to add additional testing for these risk items.
    C. Contract with the Risk Protection Insurance company to assume these risks at a cost of $500,000 per annum.
    D. Create a cross-functional team to work to reduce the impact and likelihood of these risks coming to fruition.

  • Question 167:

    Which of the following is MOST likely to influence the choice of test levels for a project?

    A. The type of project
    B. The product domain
    C. Availability of test data
    D. Test resource constraints

  • Question 168:

    You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.

    Given this information what should you conclude?

    A. More testing was needed before the production release because the defect detection percentage (DDP) was below 90%
    B. The cost of testing is high and could probably be lowered by spending more money on defect prevention
    C. The cost of testing is just right and is justified by the numbers
    D. More effort should be put on appraisal to help lower the cost of quality

  • Question 169:

    Your company, which specialises in the manufacture of luxury garden furniture to the UK market, is to embark on a project that will deliver a major update to its payment processing component, addressing improvements to functional suitability

    and performance efficiency. You have just selected a performance testing tool but it has not yet been implemented.

    A decision has been made to transfer responsibility for functional system test implementation and execution to the company's offshore test team. System test analysis and design will be performed onshore, at the company's UK head office.

    You have direct management responsibility for all test personnel, onshore and offshore.

    Which of the following is a test management activity that is MOST important for this project?

    A. Creating a resource allocation strategy
    B. Deciding which test techniques should be applied
    C. Defining an approach for usability testing
    D. Implementing the performance testing tool

  • Question 170:

    Which one of the following standards would a Test Manager be expected to understand when planning and organising activities with a Project Manager? SELECT ONE OPTION

    A. PRINCE2.
    B. CMMI.
    C. TMMI.
    D. ITIL.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISTQB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ISTQB-CTAL-TM exam preparations and ISTQB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.