  • Question 81:

    You are the test manager for Project 3 and have performed a skills assessment of your Safe as Houses' test team. You must now decide what training or skills development is required.

    The matrix shows the skill level (5 being highest, 1 lowest) for each team member. Which two of the above skills need the closest attention for potential training or development on this project? SELECT ONE OPTION

    A. Acceptance testing and Knowledge of Light Imagery software.
    B. Performance testing and Test planning for incremental life-cycles.
    C. Knowledge of Light Imagery software and Test control.
    D. Integration testing and Knowledge of Light Imagery software.

  • Question 82:

    Which two of the following are considered to be advantages when specifying detailed test conditions? SELECT ONE OPTION

    a) They may influence development activities. b) They form the basis for vertical traceability c) They are suited to agile methodology d) They can aid defect prevention e) They are quick and easy to deliver

    A. a and
    B. a and c.
    C. b and c.
    D. d and e.

  • Question 83:

    You are a new lest manager in an organization You have been asked to assess the defect process to determine if there are any efficiency improvements that could be made that would reduce the cost of quality You have started digging through the defect Information What information would be most helpful for this investigation?

    A. Defect priorities and seventies as related to time from reporting to closure
    B. Areas of the software producing the most defects
    C. Risk areas m which defects have been detected and the
    D. relationship between the risk rating of the software and the seventy of the defect
    E. The phase in which a defect was introduced versus the phase in which it was found

  • Question 84:

    In a standard defect lifecycle. which of the following states would MOST LIKELY require input or action from a member of the Test team? SELECT ONE OPTION

    A. The'deferred'state.
    B. The'cancelled' state.
    C. The 'under investigation' state.
    D. The'returned' state,

  • Question 85:

    You are assigned to test a new application being developed in-house and you have designed a set of test cases to specifically address key product risks. You will issue daily reports summarising how these test cases are progressing during test execution. When considering the audience for these reports, in which stakeholder matrix quadrant would the product's users reside?

    A. Latents (High Influence, Low Interest)
    B. Defenders (Low Influence, High Interest)
    C. Apathetic (Low Influence, Low Interest)
    D. Promoters (High Influence, High Interest)

  • Question 86:

    Which of the following statements is true regarding documentation standards? [2] A. Documentation standards are a lower priority than testing standards.

    B. Documentation standards can vary depending on the test level.

    C. Agile projects consistently use level test plans and documentation standards.

    D. Documentation standards are determined by the Project Manager.

    Correct Answer. B

  • Question 87:

    Which of the Mowing Is commonly used by a test manager to identity risks?

    A. Lines of code in the system under test
    B. Function points within the software
    C. Experience with similar projects
    D. Record/playback test automation tools

  • Question 88:

    You are the Test Manager for a new product that is being developed according to an iterative lifecycle. At this point, you have 100% of your smoke tests automated, 20% of your functional tests and 50% of your regression tests. Your

    iterations are four weeks long. You are finding that with each iteration significant maintenance is required for your automated tests and you are not able to complete the testing within the planned timeframe. The test plan you created at the

    beginning of the project indicates that all automated tests should be run before any manual tests.

    Which of the following is a reasonable change to this plan based on how the project is going? [2]

    A. Continue to run all the automation first, performing whatever maintenance is needed and then transfer testing resources from manual testing to increase the automation coverage.
    B. Run the manual tests first and maintain the automation as time allows.
    C. Continue to run the automated smoke tests first, execute the automated regression test and new manual functional tests in parallel, and discontinue automating any new functional test cases.
    D. Run the automated regression tests first then proceed with the manual and automated functional tests, discontinuing the automated smoke.

  • Question 89:

    You are a newly appointed Test Manager in an organisation that has no separate test team, no formal testing process and testing is considered to be, at best, ad-hoc in approach. The IT director is keen to introduce improvement across all areas of the organisation, not just testing. This is so that the current level of maturity can be assessed and roadmaps outlined for improving processes in a staged way. He has asked you to recommend a test process improvement model and you have suggested TMMi. Which ONE of the following is a valid reason for your recommendation? SELECT ONE OPTION

    A. It provides the fastest way to take testing to an optimized state.
    B. It provides bench-marking against industry averages using objective measurements.
    C. It helps address highest priority testing issues with limited formality.
    D. It naturally complements the IT director's process improvement goals for the organisation.

  • Question 90:

    You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks and determining the likelihood and impact of those risks. You have been testing for three months and have been able to mitigate

    75% of the high risk items. You have two weeks left in testing and you now do not expect to be able to complete all the items on the high-risk mitigation list, never mind any from the medium or low-risk lists.

    What is the most effective action you should take? [3]

    A. Use a random selection algorithm to pick tests from the high, medium, and low risk mitigation lists -thereby ensuring that each risk list has some mitigation.
    B. Present your risk mitigation progress and project status to the project's stakeholders, and request additional time or assistance in re-prioritizing the remaining high-risk items.
    C. Concentrate testing in areas that have already found numerous problems.
    D. Retest the highest risk areas to ensure no regressions have occurred.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISTQB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ISTQB-CTAL-TM exam preparations and ISTQB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.