  • Question 1141:

    What earned value (EV) measure indicates the cost efficiency of the work completed?

    A. Cost variance (CV)
    B. Cost performance index (CPI)
    C. To-complete performance index (TCPI)
    D. Variance at completion (VAC)

  • Question 1142:

    Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

    A. Project Risk Management
    B. Project Human Resource Management
    C. Project Scope Management
    D. Project Stakeholder Management

  • Question 1143:

    Which of the following is an output of Close Procurements?

    A. Accepted deliverables
    B. Organizational process assets updates
    C. Managing stakeholder expectations
    D. Performance reports

  • Question 1144:

    A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.

    Which method should the project manager adopt?

    A. Scrum
    B. SAFe
    C. Feature-driven development (FDD)
    D. Kanban

  • Question 1145:

    What is the order of the stages of project team development?

    A. Forming, Storming, Norming, Performing, and Adjourning
    B. Storming, Forming, Norming, Performing, and Adjourning
    C. Adjourning, Forming, Storming, Norming, and Performing
    D. Forming, Storming, Performing, Norming, and Adjourning

  • Question 1146:

    What is the primary purpose of Project Scope Management?

    A. Determining and managing stakeholder needs.
    B. Controlling the status of the product scope and managing changes to its baseline.
    C. Defining and controlling what is and is not included in the project.
    D. Differentiating between the product scope and project scope.

  • Question 1147:

    Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

    A. Cost Plus Award Fee Contract (CPAF)
    B. Firm-Fixed -Price Contract (FFP)
    C. Time and Material Contract (TandM)
    D. Cost Plus Incentive Fee Contract (CPIF)

  • Question 1148:

    Which of the following is an output from Control Scope?

    A. Change requests
    B. Variance analysis
    C. Accepted deliverables
    D. Requirements documentation

  • Question 1149:

    In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

    A. Ensures a thorough unit test case coverage
    B. Ensures the successful delivery of business value
    C. Ensures that the business problem is solved
    D. Ensures an accurate re ection of the stakeholders' intentions

  • Question 1150:

    What process is included in Project Integration Management?

    A. Monitor and Control Project Work
    B. Control Scope
    C. Control Schedule
    D. Develop Team

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.