  • Question 1131:

    What is the Project Schedule Management practice used to deliver incremental value to the customer?

    A. Resource optimization
    B. Iterative scheduling with a backlog
    C. On-demand scheduling
    D. Critical path method

  • Question 1132:

    In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

    A. Matrix - strong
    B. Matrix - balanced
    C. Virtual
    D. Functional

  • Question 1133:

    The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

    A. a control chart.
    B. baseline.
    C. Create WBS.
    D. decomposition.

  • Question 1134:

    Which of the following activities are included as part of a project manager's responsibilities?

    A. Direct, control, and focus on structure.
    B. Inspire, engage, and build relationships with people.
    C. Control, maintain project status, and develop.
    D. Problem solve, achieve the bottom line, and focus on success.

  • Question 1135:

    Which type of project life cycle uses an iteration plan?

    A. Agile
    B. Predictive
    C. Waterfall
    D. Product

  • Question 1136:

    What are the components of the "triple constraint "?

    A. Scope, time, requirements
    B. Resources, time, cost
    C. Scope, management, cost
    D. Scope, time, cost

  • Question 1137:

    Change requests are processed for review and disposition according to which process?

    A. Control Quality
    B. Control Scope
    C. Monitor and Control Project Work
    D. Perform Integrated Change Control

  • Question 1138:

    A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities.

    What are the four elements of a RACI chart?

    A. Recommend, approve, coordinate, and inform
    B. Recommend, accountable, consult, and inform
    C. Responsible, accountable, consult, and inform
    D. Responsible, accountable, coordinate, and inform

  • Question 1139:

    The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

    A. Planning.
    B. Executing,
    C. Monitoring and Controlling.
    D. Closing.

  • Question 1140:

    An input to the Create WBS process is a:

    A. project charter.
    B. stakeholder register.
    C. project scope statement.
    D. requirements traceability matrix.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.