  • Question 1161:

    Which of the following is an input to the Plan Risk Responses process?

    A. Risk urgency assessment
    B. Organizational process assets
    C. Risk register
    D. Schedule management plan

  • Question 1162:

    A complete set of concepts, terms, and activities that make up an area of specialization is known as:

    A. a Knowledge Area
    B. a Process Group
    C. program management
    D. portfolio management

  • Question 1163:

    Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

    A. Internal enterprise environmental factor
    B. Risk register database
    C. External enterprise environmental factor
    D. Organizational process asset

  • Question 1164:

    Which tool or technique is used in the Plan Scope Management process?

    A. Document analysis
    B. Observations
    C. Product analysis
    D. Expert judgment

  • Question 1165:

    DRAG DROP

    Match each process in Project Stakeholder Management with its associated Process Group.

    Select and Place:

  • Question 1166:

    Which element does a project charter contain?

    A. Management reserves
    B. Work breakdown structure
    C. Stakeholder list
    D. Stakeholder register

  • Question 1167:

    Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?

    A. Earned value performance
    B. Trend analysis
    C. Cost-benefit analysis
    D. Variance analysis

  • Question 1168:

    Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

    A. Project
    B. Functional
    C. Program
    D. Portfolio

  • Question 1169:

    Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?

    A. In uence and challenge
    B. Innovation and administration
    C. Leadership and management
    D. Engagement and guidance

  • Question 1170:

    Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

    A. Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.
    B. Make surveys among the stakeholders and meet with the team once a month.
    C. Create a social network and post news there.
    D. Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.