  • Question 1151:

    The zero duration of milestones in project planning occurs because milestones:

    A. Are unpredictable and challenge the Plan Schedule Management process.
    B. Occur at random times in the project plans.
    C. Represent a moment in time such as a significant project point or event.
    D. Represent both significant and insignificant points in the project and are difficult to anticipate.

  • Question 1152:

    Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

    A. Force/direct
    B. Withdraw/avoid
    C. Compromise/reconcile
    D. Collaborate/problem solve

  • Question 1153:

    What is an output of the Control Costs process?

    A. Cost management plan
    B. Cost baseline
    C. Change requests
    D. Basis of estimates

  • Question 1154:

    Which of the following is a goal of the project charter?

    A. Detail requirements for the project tasks.
    B. List all tasks the team should perform in the project.
    C. Empower the project manager to manage the project.
    D. Develop a business case to support the project.

  • Question 1155:

    Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?

    A. Activities
    B. Milestone list
    C. Work breakdown structure (WBS)
    D. Work packages

  • Question 1156:

    The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

    A. dictionary.
    B. chart.
    C. report.
    D. register.

  • Question 1157:

    When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

    A. event.
    B. response.
    C. perception.
    D. impact.

  • Question 1158:

    Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

    A. Exploit
    B. Share
    C. Enhance
    D. Transfer

  • Question 1159:

    A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype.

    Who should the project manager invite to provide expert advice?

    A. The major stakeholders nominated by the project sponsor
    B. The usual review participants holding recognized certifications
    C. The senior experts with high status in the academic community
    D. The subject matter experts (SMEs) identified in the stakeholder register

  • Question 1160:

    The project manager is creating the communications management plan. Which group of inputs is required to begin?

    A. Work performance reports, change requests, and risk register
    B. Work performance data, project documents, and stakeholder engagement plan
    C. Project charter, project management plan, and project documents
    D. Work performance data, stakeholder register, and team management plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.