Question 11:
In what sequence are the steps of material requirements planning performed in SAP ECC?
A. 1. Net requirements calculation 2. Lot sizing 3. Determination of the procurement type 4. Scheduling B. 1. Calculation of safety stock 2. Lot sizing 3. Scheduling 4. Determination of the procurement type C. 1. Availability check 2. Lot sizing 3. Determination of the procurement type 4. Scheduling D. 1. Net requirements calculation 2. Lot sizing 3. Scheduling 4. Determination of the procurement type
A. 1. Net requirements calculation 2. Lot sizing 3. Determination of the procurement type 4. Scheduling
Question 12:
Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)
A. Reorder point planned materials can be included in long-term planning. B. In case of external procurement, long-term planning creates purchase requisitions. C. A planning scenario must be released to use it in long-term planning. D. Long-term planning generally is operational planning of important components.
A. Reorder point planned materials can be included in long-term planning. C. A planning scenario must be released to use it in long-term planning.
Question 13:
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)
A. General values from work scheduling view in the material master B. Standard value from operation in task list C. User-defined field from operation in task list D. General operation values in task list E. General item values in bill of materials
B. Standard value from operation in task list C. User-defined field from operation in task list D. General operation values in task list
Question 14:
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
A. Rescheduling the operation B. Posting the goods receipt for the production order C. Confirming the operation D. Setting the status technically complete (TECO) E. Reducing the order quantity
C. Confirming the operation D. Setting the status technically complete (TECO) E. Reducing the order quantity
Question 15:
What do you have to consider regarding lot size procedures?
A. The procurement quantity of a lot size procedure can be specified using a safety time period profile. B. If a long-term lot size is used, procurement is conducted with a long-term perspective. C. The lot size quantity can be influenced using a minimum lot size and the rounding profile. D. If a make-to-order production strategy is used, only the lot-for-lot (exact) lot size can be applied.
C. The lot size quantity can be influenced using a minimum lot size and the rounding profile.
Question 16:
Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? (Choose three.)
A. Automatic generation of a transport order B. Material directory C. Pull list D. Pick list E. Logistics Information System (LIS)
A. Automatic generation of a transport order C. Pull list D. Pick list
Question 17:
In your company planning strategies are used in the SAP-ECC demand management that are based on consumption. Which of the following statements about consumption is true? (Choose two.)
A. A consumption situation is dynamic and is always restructured with the planning run. B. Consumption can also take place between order reservations and planned independent requirements, depending on the strategy. C. Consumption always takes place on the material level between the planned independent requirements and the planned orders. D. The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
B. Consumption can also take place between order reservations and planned independent requirements, depending on the strategy. D. The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
Question 18:
Which of the following are properties of ECC Multi-Site Planning? (Choose two.)
A. Both withdrawal from alternative plant and withdrawal from another plant are defined via special procurement keys. B. The use of scope of planning (cross-plant total planning) is mandatory for Multi-Site Planning. C. When using one-step stock transfer posting, transfer stock is created in the receiving plant. D. When using two-step stock transport order with delivery, the receiving plant is defined as a customer.
A. Both withdrawal from alternative plant and withdrawal from another plant are defined via special procurement keys. D. When using two-step stock transport order with delivery, the receiving plant is defined as a customer.
Question 19:
Which of the following elements can be used in a process order? (Choose three)
A. Process instructions B. Parallel sequences C. Relationships D. Suboperations E. Phases
A. Process instructions C. Relationships E. Phases
Question 20:
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.
Which of the following scenarios are applicable in this case? (Choose two)
A. You can enter the strategy group 40 in the material master, but the requirement type is not changed automatically for existing requirements. B. You must change the requirement type for planning strategy 10 to VSF in Customizing. The requirement type for all existing requirements is then changed by the next planning run. C. You can change the strategy group from 10 to 40 for the existing production plan in the material master, and the requirement type for all requirements is changed automatically. D. You can enter the strategy group 40 in the material master and change the present requirement for the product manually in the production plan.
A. You can enter the strategy group 40 in the material master, but the requirement type is not changed automatically for existing requirements. D. You can enter the strategy group 40 in the material master and change the present requirement for the product manually in the production plan.
Nowadays, the certification exams become more and more important and required by more and more
enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare
for the exam in a short time with less efforts? How to get a ideal result and how to find the
most reliable resources? Here on Vcedump.com, you will find all the answers.
Vcedump.com provide not only SAP exam questions,
answers and explanations but also complete assistance on your exam preparation and certification
application. If you are confused on your C_TSCM42_67 exam preparations
and SAP certification application, do not hesitate to visit our
Vcedump.com to find your solutions here.