  • Question 1:

    Which function is supported by production orders?

    A. Automatic selection of a work center at order release
    B. Automatic creation of transfer orders at order release
    C. Automatic reading of PP master data at order release
    D. Automatic printing of order documents at order creation

  • Question 2:

    An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon.

    What procedure would you recommend to the project team for setting the planning horizon on the system side?

    A. The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.
    B. The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.
    C. The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.
    D. The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.

  • Question 3:

    The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned

    order is set to a later date than the one for the sales order.

    However, a corresponding rescheduling exception message does not appear.

    What could be the reasons? (Choose two)

    A. The delta between the availability dates falls within the tolerance window defined in Customizing.
    B. The fixed planned order is outside the rescheduling horizon.
    C. Requirements planning has not been carried out.
    D. The MRP elements are linked via fixed pegging.

  • Question 4:

    Which property applies for consumption with planning strategy 40 (planning with final assembly)?

    A. Consumption can result in subsequent adjustments of planned receipts.
    B. Consumption can reduce the originally planned production quantity.
    C. Consumption takes place with the planning material.
    D. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.

  • Question 5:

    You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.

    How can you fulfill these requirements in SAP ECC? (Choose two)

    A. Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material.
    B. Use strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
    C. Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
    D. Use strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

  • Question 6:

    What data can be posted directly via the Plant Data Collection (PP-PDC) interface?

    A. Goods receipts
    B. Maintenance notifications
    C. Confirmations
    D. Goods issues

  • Question 7:

    Which of the following are characteristics of ECC master production scheduling (MPS)? (Choose three)

    A. MPS items are planned in a standard MRP run.
    B. The planning of MPS and non-MPS items is always carried out in one planning run.
    C. Non-MPS items can be taken into consideration by an MPS run.
    D. MPS items can be defined on plant level.
    E. MPS items can be defined on MRP area level.

  • Question 8:

    Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.

    How is the resulting firming interval specified in this scenario?

    A. By the planning time fence from the material master
    B. By the firming mechanism with the longer firming interval
    C. By the manual firming date
    D. It is predefined in Customizing.

  • Question 9:

    Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?

    A. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.
    B. Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.
    C. Assign an appropriate availability checking rule to the material master for the product.
    D. Activate the availability check and assign an overall profile in the production scheduling profile.

  • Question 10:

    Which functions can be triggered before releasing a production order? (Choose three)

    A. Selection of a routing
    B. Selection of a BOM
    C. Stock determination
    D. Confirmation
    E. Scheduling

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_67 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.