  • Question 101:

    You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling). Which of the following properties for the resulting dependent requirements applies?

    A. In multi-level backward scheduling, dependent requirements are calculated to the exact second.
    B. If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.
    C. When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.
    D. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.

  • Question 102:

    Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order. Which BOM item category must you set to fulfill this requirement?

    A. D (document item)
    B. E (external procurement)
    C. M (phantom material)
    D. N (non-stock item)

  • Question 103:

    The final assembly of a finished product should only be triggered when a customer order arrives.

    Which planning strategy for the finished product do you use?

    A. Planning with make-to-stock (strategy 10)
    B. Planning at the assembly level (strategy 70)
    C. Planning without final assembly (strategy 50)
    D. Planning with final assembly (strategy 40)

  • Question 104:

    The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?

    A. Substitute sequence
    B. Alternative sequence
    C. Parallel sequence
    D. Standard sequence

  • Question 105:

    Where in the SAP ECC system can you define production versions?

    A. In the material master
    B. In the routing
    C. In the bill of material
    D. In the work center

  • Question 106:

    In which of the following objects can you activate back flushing for production orders? (Choose three)

    A. Work center
    B. Routing
    C. Material master (finished product)
    D. Material master (component)
    E. Production scheduling profile

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_67 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.