SAP C_TSCM42_66 Online Questions & Answers

  • Question 71:

    Which of the following master data is necessary for the creation of material reservations for production orders?

    A. Material master records
    B. Production/resource tools
    C. Routings
    D. Production versions

  • Question 72:

    Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?

    A. Lead time scheduling cannot take place.
    B. Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.
    C. Requirements planning creates an appropriate exception message in basic dates scheduling.
    D. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.

  • Question 73:

    Which functions can be triggered before releasing a production order? (Choose three)

    A. Selection of a routing
    B. Selection of a BOM
    C. Stock determination
    D. Confirmation
    E. Scheduling

  • Question 74:

    Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order. Which BOM item category must you set to fulfill this requirement?

    A. D (document item)
    B. E (external procurement)
    C. M (phantom material)
    D. N (non-stock item)

  • Question 75:

    Which of the following features are offered by MRP areas in SAP ECC? (Choose two)

    A. A storage location may be assigned to different MRP areas.
    B. An MRP area may include different storage locations.
    C. Make-to-order production is supported by storage location MRP areas.
    D. Subcontracting is supported by MRP areas.

  • Question 76:

    Which of the following properties applies to multi-site planning in SAP ECC?

    A. When using one-step stock transfer posting, transfer stock is created in the receiving plant.
    B. Multi-site planning can be activated using the corresponding planning strategy.
    C. Both withdrawal from an alternative plant and stock transfer from another plant are defined via special procurement keys.
    D. The use of "scope of planning" is always mandatory for multi-site planning.

  • Question 77:

    Which function is supported by production orders?

    A. Automatic selection of a work center at order release
    B. Automatic creation of transfer orders at order release
    C. Automatic reading of PP master data at order release
    D. Automatic printing of order documents at order creation

  • Question 78:

    What do you have to consider regarding lot size procedures?

    A. The procurement quantity of a lot size procedure can be specified using a safety time period profile.
    B. If a long-term lot size is used, procurement is conducted with a long-term perspective.
    C. The lot size quantity can be influenced using a minimum lot size and the rounding profile.
    D. If a make-to-order production strategy is used, only the lot-for-lot (exact) lot size can be applied.

  • Question 79:

    During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system. Which of the following procurement type properties are valid? (Choose two)

    A. If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production.
    B. Procurement types E (in-house production) and F (external procurement) always have to be further refined with special procurement types.
    C. Procurement types E (in-house production), F (external procurement), or X (both procurement types) can be selected for a material independent of the material type.
    D. If procurement type E (in-house production) is set, external procurement may still be possible, depending on the material type.

  • Question 80:

    You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC. On which specifications is the dynamic safety stock calculation based?

    A. The static safety stock and the material forecast
    B. The average daily demand and the safety time
    C. The average daily demand and the desired range of coverage
    D. The static safety stock per day and the safety time

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_66 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.