Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
A. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.You select the master data for production orders via production versions. Which information is contained in a production version?
A. The explosion dates for the routing and BOMWhat can you use to organize material staging for production orders? (Choose three)
A. Material documentsWhat functions can you use for sub operations? (Choose two)
A. CostingWhen analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling. Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
A. Total planning onlineWhich repetitive manufacturing options can you use to carry out line loading in the SAP ECC system, and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)
A. Automatic selection of the production line assigned to the MRP group used during material requirements planning (MRP)The availability check during production order creation should use a different scope of check than during order release. How can you fulfill this requirement?
A. Maintain appropriate checking rules in checking control for order creation and order release.In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
-Start: 7:00:00 a.m.
-End: 3:00:00 p.m.
-Break duration: 1 hour
-Rate of utilization: 80%
-Overload: 110%
-
Number of individual capacities: 1 How large is the standard available capacity?
A. 8 hoursThe stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order. However, a corresponding rescheduling exception message does not appear.
What could be the reasons? (Choose two)
A. The delta between the availability dates falls within the tolerance window defined in Customizing.The final assembly of a finished product should only be triggered when a customer order arrives. Which planning strategy for the finished product do you use?
A. Planning with make-to-stock (strategy 10)Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_66 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.