  • Question 51:

    In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type. What does a firming type define? (Choose two)

    A. Handling new requirements within the planning time fence.
    B. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.
    C. Handling existing procurement proposals outside the planning time fence.
    D. Handling existing procurement proposals within a planning time fence.

  • Question 52:

    Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.

    How is the resulting firming interval specified in this scenario?

    A. By the firming mechanism that spans further into the future.
    B. By the manual firming date.
    C. It is predefined in Customizing.
    D. By the planning time fence from the material master.

  • Question 53:

    Which of the following statements about the planning functions available in SAP ECC is correct?

    A. Master production scheduling (MPS) refers to preferred planning of important materials.
    B. Material requirements planning (MRP) includes automatic capacity leveling.
    C. Long-term planning (LTP) is a long-term form of forecast planning.
    D. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.

  • Question 54:

    Which properties does ECC Master Production Scheduling (MPS) have? (Choose three)

    A. MPS items can be taken into consideration by a standard MRP run.
    B. Non-MPS items can be taken into consideration by an MPS run.
    C. The planning of MPS and Non-MPS items is always carried out in one planning run.
    D. MPS items can be defined on MRP Area level.
    E. MPS items can be defined on plant level.

  • Question 55:

    What option for selecting a routing exists when creating a production order?

    A. Automatic selection based on settings in the production scheduling profile
    B. Manual selection based on the list of routings maintained in the material master
    C. Automatic selection of a reference operation set
    D. Manual selection based on settings in the order type-dependent parameters

  • Question 56:

    The stock/requirements list for a finished product contains only one customer order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date of the fixed planned order is set to a later date compared to the one of the customer order. However, a corresponding rescheduling exception message does not occur.

    What could be the reason? (Choose two)

    A. Requirement planning has not been carried out.
    B. The MRP elements are linked via fixed pegging.
    C. The fixed planned order is outside the rescheduling horizon.
    D. The delta between the availability dates falls within the tolerance window defined in Customizing.

  • Question 57:

    Which of the following elements can be used in a process order? (Choose three)

    A. Phases
    B. Process instructions
    C. Relationships
    D. Suboperations
    E. Parallel sequences

  • Question 58:

    You select the master data for production orders via production versions.

    Which information is contained in a production version?

    A. The control parameters for selecting routings and BOM
    B. The default order type to be used
    C. The routing and BOM alternatives to be used
    D. The explosion dates for the routing and BOM

  • Question 59:

    Where can you define the valid receivers for production order costs?

    A. In the valuation variant
    B. In the production scheduling profile
    C. In the settlement profile
    D. In the costing variant

  • Question 60:

    Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order. Which BOM item category must you set to fulfill this requirement?

    A. D (document item)
    B. M (phantom material)
    C. N (non-stock item)
    D. E (external procurement)

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_65 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.