  • Question 11:

    The availability check during production order creation should use a different scope of check than during order release. How can you fulfill this requirement?

    A. Maintain appropriate checking rules in checking control for order creation and order release.
    B. Maintain appropriate availability checking rules in the production scheduling profile.
    C. Maintain an appropriate availability checking group in the material master.
    D. Maintain appropriate availability checking rules in the order type-dependent parameters.

  • Question 12:

    You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?

    A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning
    B. Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning
    C. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning
    D. Demand management -> Sales and operations planning -> Capacity planning -> Long-term planning -> Material requirements planning

  • Question 13:

    During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system.

    Which of the following procurement type properties are valid? (Choose two)

    A. If procurement type E (in-house production) is set, external procurement may still be possible depending on the material type.
    B. A material's procurement type can be freely selected between E (in-house production), F (external procurement) and X (both procurement types) independent of material type.
    C. Procurement types E (in-house production) and F (external procurement) have to be further refined with special procurement types.
    D. If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production.

  • Question 14:

    You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.

    What do you have to consider in this scenario?

    A. Planned orders that are created by requirements planning are shifted to the end of the planning time fence.
    B. Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
    C. The MRP controller cannot create planned orders within the planning time fence.
    D. Planned orders are created within the planning time fence and automatically firmed by requirements planning.

  • Question 15:

    Which of the following properties applies to multi-site planning in SAP ECC?

    A. Multi-site planning can be activated using the corresponding planning strategy.
    B. Both withdrawal from alternative plant and stock transfer from another plant are defined via special procurement keys.
    C. The use of "scope of planning" (cross-plant total planning) is mandatory for multi-site planning.
    D. When using one-step stock transfer posting, transfer stock is created in the receiving plant.

  • Question 16:

    You maintained the planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months you have planned requirements with requirement type LSF (derived from the main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.

    Which of the following statements are applicable in this case? (Choose two)

    A. You can enter the strategy group 40 in the material master and change the present requirement for the product manually in the production plan.
    B. You must change the requirement type for planning strategy 10 to VSF in Customizing. The requirement type for all existing requirements is then changed by the next planning run.
    C. You can change the strategy group from 10 to 40 for the existing production plan in the material master, and the requirement type for all requirements is changed automatically.
    D. You can enter the strategy group 40 in the material master, but the requirement type is not changed automatically for existing requirements.

  • Question 17:

    What sequence do you follow in master data maintenance to define the production of a material?

    A. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing
    B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
    C. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
    D. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center

  • Question 18:

    Which statements regarding SAP ECC long-term planning (LTP) are correct? (Choose two)

    A. In case of external procurement, LTP creates purchase requisitions.
    B. Reorder point planned materials can be included in LTP.
    C. Generally, LTP is operational planning of important components.
    D. A planning scenario must be released to use it in LTP.

  • Question 19:

    Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?

    A. Lead time scheduling cannot take place.
    B. Requirements planning creates an appropriate exception message in basic dates scheduling.
    C. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
    D. Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.

  • Question 20:

    You want to use the function "Read PP master data" in the production order. However, while calling the function you receive an error message. What could be the reason?

    A. Goods movements have been posted.
    B. Order papers have been printed.
    C. The material availability check has been performed.
    D. The production order has been released.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_65 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.