SAP C_TSCM42_65 Online Questions & Answers

  • Question 1:

    Which of the following consequences result when a production order is set to Technically Complete (TECO)? (Choose three)

    A. Confirmations are no longer permitted.
    B. Reservations are no longer relevant for material requirements planning.
    C. The order and its operations receive the system status Locked (LKD).
    D. Capacity requirements are set to null.
    E. The order is no longer relevant for material requirements planning.

  • Question 2:

    During the processing of production orders planned and actual costs are determined. On which of the following objects can you collect these costs? (Choose two)

    A. Work center
    B. Planned order
    C. Product cost collector
    D. Production order

  • Question 3:

    Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three) A. Finite capacity scheduling

    B. Setup time reduction
    C. Midpoint scheduling
    D. Lot size optimization
    E. Batch size optimization

  • Question 4:

    A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.

    Which of the following statements are true for the two lists at this stage? (Choose two)

    A. The MRP list displays the production order.
    B. The stock/requirements list displays the production order.
    C. The stock/requirements list was updated at the precise time it was accessed.
    D. The MRP list has the status "processed".

  • Question 5:

    Which of the following statements about consumption are correct? (Choose two)

    A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
    B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
    C. Consumption is restructured with the planning run.
    D. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.

  • Question 6:

    You want to send production order-related data like confirmations, goods receipts, goods issues, and other user-specific actual data from an external process control system to SAP ECC. How can you fulfill this requirement?

    A. Use the core interface (CIF).
    B. Use the service application interface (SAPI).
    C. Use the PI-PCS interface.
    D. Use the PP-PDC interface.

  • Question 7:

    Which of the following requirements is supported by using process orders?

    A. Linkage of documents to orders
    B. Use of reference operation sets
    C. Use of production/resource tools
    D. Documentation of the production using an electronic batch record

  • Question 8:

    Where in the SAP ECC system can you define production versions?

    A. In the bill of material
    B. In the work center
    C. In the material master
    D. In the routing

  • Question 9:

    In which scenario will the error message shown in the attached screenshot occur?

    A. The selection method is set to "selection only by production version" in the material master.
    B. The routing is not valid at the explosion date.
    C. The Customizing for the order type is set to manual routing selection and a valid routing exists.
    D. The material master is set to manual routing selection and a valid routing exists.

  • Question 10:

    When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.

    What further tasks do you perform before you can use requirements planning in plant 1000 in SAP ECC?

    A. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in Customizing.
    B. Set up the planning files in Customizing and specify the plant parameters for plant 1000 in Customizing of the MRP group.
    C. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in the MRP views in material master.
    D. Activate requirements planning in Customizing for MRP areas in plant 1000 and specify the plant parameters for plant 1000 in the MRP views in material master.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_65 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.