AACE International AACE International Certifications AACE-PSP Questions & Answers

  • Question 41:

    If all other work proceeds according to the Baseline plan, how many times will the critical path change?

    A. 2.

    B. 1.

    C. Does not change.

    D. 3.

  • Question 42:

    Which of the following are NOT normally included in the project scope statement, either directly or by reference?

    A. Project objectives in terms of cost, schedule and quality measures

    B. Project contract between the contractor and owner

    C. Project justification

    D. Project deliverables

  • Question 43:

    Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

    A. Non-excusable delay

    B. Compensable delay

    C. Non-compensable delay

    D. Excusable delay

  • Question 44:

    In a "crashed" schedule, which is a chain of activities that precede activity 2004?

    A. 1001, 2001, 2002, 2003

    B. 2001, 2002, 2003, 2007

    C. 1001, 2002, 2003

    D. 1001, 2002, 2002, 2003, 3001

  • Question 45:

    Activity C is a

    A. Contentious activity.

    B. Continuous activity.

    C. 1-day activity.

    D. Milestone.

  • Question 46:

    The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

    A. Budget at completion (BAC)

    B. Budgeted cost of work performed (BCWP)

    C. Estimate to complete (ETC)

    D. Estimate at completion (EAC)

  • Question 47:

    The work breakdown structure is used to organize

    A. "Smart activity ID codes" representing similar items of scheduled work

    B. The chart of accounts

    C. Similar activity coding of schedule activities

    D. The smallest defined work packet

  • Question 48:

    Identify the late finish to develop plans and specs.

    A. 9 months.

    B. 10 months.

    C. 8 months.

    D. 7 months.

  • Question 49:

    Project delays are best analyzed

    A. After either the contractor or the owner acknowledges ^responsibility for the delay.

    B. Contemporaneously with the delay.

    C. By an expert after the project is finished when complete records are available and the impact is known.

    D. Late in the project.

  • Question 50:

    What is the relationship depicted between Activity G and Activity H?

    A. You cannot tell with the supplied information.

    B. Start-to-start.

    C. Finish-to-start.

    D. Finish-to-finish.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only AACE International exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your AACE-PSP exam preparations and AACE International certification application, do not hesitate to visit our Vcedump.com to find your solutions here.