Under which circumstances should multiple projects be grouped in a program?
A. When they are needed to accomplish a set of goals and objectives for an organization
B. When they have the same project manager and the same organizational unit
C. When they have the same scope, budget, and schedule
D. When they are from the same unit of the organization
A project team member is estimating the cost of an activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?
A. Bottom-up estimating
B. Three-point estimating
C. Analogous estimating
D. Parametric estimating
Which task will a project manager undertake while conducting Project Resource Management?
A. Identify the different aspects of the team to manage and control physical resources efficiently
B. Procure equipment, materials, facilities, and infrastructure for the project
C. Train the team members in project skill sets
D. Define the roles and responsibilities of each team member
Which knowledge area includes the processes to identify, define, and unify the various project management processes?
A. Project Integration Management
B. Project Communications Management
C. Project Quality Management
D. Project Risk Management
A project manager is working on project cost management. The following information is current:
Planned value = 30
Actual cost = 35
Earned value = 28
Considering this data, which project indicator is correct?
A. Schedule Variance (SV) = 2
B. Cost Performance Index (CPI) = 0.80
C. Schedule Performance Index (SPI) = 1.93
D. Cost Variance (CV) = 7
Which of the following set of items belongs to the communications management plan?
A. Escalation processes and meeting management
B. Project schedule and glossary of common terminology
C. Escalation processes and stakeholder communication requirements
D. Interactive communication model and information to be communicated
Which statement about accepted deliverables is correct?
A. Project deliverables are completed and checked for correctness through the Control Quality process
B. Project deliverables meet the acceptance criteria and are formally signed off and approved by the customer or sponsor
C. Project deliverables meet the acceptance criteria and have been checked through the Control Quality process
D. Projects deliverables are registered as a result of all work packages that are checked and delivered and which meet the acceptance criteria
Tailoring considerations for project scope management may include:
A. requirements management, stability of requirements, development approach, and validation and control
B. WBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables
C. business needs, product descriptions, project restrictions, and project management plan
D. issues defining and controlling what is included in the project, verified deliverables, and quality reports
What is one of the main purposes of the project charter?
A. Formal authorization of the existence of the project
B. Formal acceptance of the project management plan
C. Formal approval of the detailed project budget D. Formal definition of stakeholder roles and responsibilities
Which type of project life cycle uses an iteration plan?
A. Agile
B. Predictive
C. Waterfall
D. Product
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.