  • Question 1071:

    The review of a seller's progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

    A. Work performance information.

    B. Inspections and audits.

    C. A contract change control system.

    D. Procurement performance reviews.

  • Question 1072:

    Which statement summarizes the role of the change control board?

    A. The change control board is responsible for presenting the change for approval

    B. The change control board will analyze the change impact in terms of cost and schedule

    C. The change control board is responsible for managing the change management and configuration management systems

    D. The change control board is responsible for reviewing and approving changes to the project

  • Question 1073:

    Which tool or technique is used in the Develop Project Management Plan process?

    A. Pareto diagram

    B. Performance reporting

    C. SWOT analysis

    D. Expert judgment

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.