Which is the appropriate tool to identify the possible correlation between two elements in a process?
A. Scatter diagram
B. Cause-and-effect diagram
C. Histogram
D. Control charts
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
A. Acquire Resources
B. Control Resources
C. Manage Team
D. Develop Team
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
A. create the project management plan
B. identify the project objectives
C. review and update stakeholder engagement
D. create the schedule baseline
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment.
How can the project manager ensure that this will work for the project?
A. Take control of all decisions and product planning
B. Build a team that can respond to changes within a collaborative, decision-making environment
C. Promote a team with a narrow specialization within a hierarchical environment
D. Delegate project decisions to the product owner and sponsor
Which of the following tasks focuses on decomposing work packages?
A. Adjust duration estimates
B. Define activities
C. Complete rolling wave planning
D. Develop milestone list
Which key benefit can a project manager obtain by identifying stakeholders?
A. Identify the appropriate focus for engagement of each stakeholder
B. Assess the risk exposure for each stakeholder
C. Map stakeholder power and influence grid
D. Identify the appropriate channels of communication with all stakeholders
Which tool should a project manager consider to deal with multiple sources of risk?
A. An updated risk register
B. Risk breakdown structure
C. Issue log
D. Stakeholder register
According to PMBOK, the definition of Plan Risk Management is: A. Develop strategies and agreeing on actions to address overall and individual risk and exposure
B. Define how to conduct risk management activities for a project
C. Implement agreed-upon risk response plans
D. Analyze the impact of identified individual risk and other sources of uncertainty on overall project objectives
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?
A. Work performance information
B. Bidder conferences
C. Complexity of procurement
D. Procurement management plan
Which format can a network diagram take?
A. Flow chart
B. Control chart
C. Affinity diagram
D. Cause-and-effect diagram
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.