  • Question 241:

    What is a hierarchically organized depiction of the identified project risks arranged by risk category?

    A. Risk register

    B. Risk breakdown structure (RBS)

    C. Risk management plan

    D. Risk category

  • Question 242:

    Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

    A. Histogram

    B. Quality audits

    C. Benchmarking

    D. Performance measurement analysis

  • Question 243:

    Which of the following investigates the likelihood that each specific risk will occur?

    A. Risk register

    B. Risk audits

    C. Risk urgency assessment

    D. Risk probability and impact assessment

  • Question 244:

    Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

    A. Mitigate

    B. Transfer

    C. Share

    D. Avoid

  • Question 245:

    Which activity is an input to the Conduct Procurements process?

    A. Organizational process assets

    B. Resource availability

    C. Perform Integrated Change Control

    D. Team performance assessment

  • Question 246:

    What is the number of stakeholders, if the project has 28 potential communication channels?

    A. 7

    B. 8

    C. 14

    D. 16

  • Question 247:

    Information collected on the status of project activities being performed to accomplish the project work is known as what?

    A. Project management information system

    B. Work performance information

    C. Work breakdown structure

    D. Variance analysis

  • Question 248:

    Which of the following tools or techniques is used for Estimate Activity Durations?

    A. Critical path method

    B. Rolling wave planning

    C. Precedence diagramming method

    D. Parametric estimating

  • Question 249:

    Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

    A. Project Integration Management

    B. Project Communications Management

    C. Project Information Management System (PIMS)

    D. Project Scope Management

  • Question 250:

    When would resource leveling be applied to a schedule model?

    A. Before constraints have been identified

    B. Before it has been analyzed by the critical path method

    C. After it has been analyzed by the critical path method

    D. After critical activities have been removed from the critical path

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.