  • Question 251:

    Which of the following statements correctly characterizes pull communication?

    A. It includes letters, memos, reports, emails, and faxes.

    B. It requires recipients to access communication content at their own discretion.

    C. It is the most efficient way to ensure a common understanding among all participants.

    D. It is primarily used when the volume of information to be transferred is minimal.

  • Question 252:

    Which of the following is an output of the Monitor and Control Project Work process?

    A. Change requests

    B. Performance reports

    C. Organizational process assets

    D. Project management plan

  • Question 253:

    Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

    A. Complete project phase

    B. Project life

    C. The project life cycle

    D. Project cycle

  • Question 254:

    Which schedule network analysis technique modifies the project schedule to account for limited resources?

    A. Human resource planning

    B. Fast tracking

    C. Critical chain method

    D. Rolling wave planning

  • Question 255:

    Which of the following is a tool and technique for Estimate Activity Durations?

    A. Parametric estimating

    B. Monte Carlo analysis

    C. Alternatives analysis

    D. Bottom-up estimating

  • Question 256:

    Which of the following is contained within the communications management plan?

    A. An organizational chart

    B. Glossary of common terminology

    C. Organizational process assets

    D. Enterprise environmental factors

  • Question 257:

    What is the term assigned to products or services having the same functional use but different technical characteristics?

    A. Scope

    B. Quality

    C. Specification

    D. Grade

  • Question 258:

    When is a Salience Model used?

    A. In a work breakdown structure (WBS)

    B. During quality assurance

    C. In stakeholder analysis

    D. During quality control (QC)

  • Question 259:

    What cost control technique is used to compare actual project performance to planned or expected performance?

    A. Cost aggregation

    B. Trend analysis

    C. Forecasting

    D. Variance analysis

  • Question 260:

    An input required in Define Scope is an organizational:

    A. structure.

    B. process asset.

    C. matrix.

    D. breakdown structure.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.