PMI CAPM PMI-100 Questions & Answers

  • Question 231:

    Which enterprise environmental factors are considered during cost estimating?

    A. Market conditions and published commercial information

    B. Company structure and market conditions

    C. Commercial information and company structure

    D. Existing human resources and market conditions

  • Question 232:

    Who, along with the project manager, is supposed to direct the performance of the planned project

    activities and manage the various technical and organizational interfaces that exist within the project?

    A. The customer and functional managers

    B. The risk owners and stakeholders

    C. The sponsors and stakeholders

    D. The project management team

  • Question 233:

    In an organization with a projectized organizational structure, who controls the project budget?

    A. Functional manager

    B. Project manager

    C. Program manager

    D. Project management office

  • Question 234:

    Organizations perceive risks as:

    A. events that will inevitably impact project and organizational objectives.

    B. the effect of uncertainty on their project and organizational objectives.

    C. events which could have a negative impact on project and organizational objectives.

    D. the negative impact of undesired events on their project and organizational objectives.

  • Question 235:

    The Define Scope process is in which of the following Process Groups?

    A. Initiating

    B. Planning

    C. Monitoring and Controlling

    D. Executing

  • Question 236:

    Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

    A. Organizational standard processes

    B. Marketplace conditions

    C. Historical information

    D. Templates

  • Question 237:

    What is the difference between the critical path and the critical chain?

    A. Scope changes

    B. Resource limitations

    C. Risk analysis

    D. Quality audits

  • Question 238:

    Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

    A. Analogous

    B. Parametric

    C. Bottom-up

    D. Top-down

  • Question 239:

    During which process group is the quality policy determined?

    A. Initiating

    B. Executing

    C. Planning

    D. Controlling

  • Question 240:

    Taking out insurance in relation to risk management is called what?

    A. Transference

    B. Avoidance

    C. Exploring

    D. Mitigation

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.