PMI CAPM PMI-100 Questions & Answers

  • Question 261:

    Which of the following is TRUE about most project life cycles?

    A. Staffing level is highest at the start.

    B. The stakeholders' influence is highest at the start.

    C. The level of uncertainty is lowest at the start.

    D. The cost of changes is highest at the start.

  • Question 262:

    Which of the following is an input to Direct and Manage Project Execution?

    A. Requested changes

    B. Approved change requests

    C. Work performance information

    D. Implemented defect repair

  • Question 263:

    Which tools or techniques will a project manager use for Develop Project Team?

    A. Negotiation

    B. Roles and responsibilities

    C. Recognition and rewards

    D. Prizing and promoting

  • Question 264:

    Which illustrates the connection between work that needs to be done and its project team members?

    A. Work breakdown structure (WBS)

    B. Network diagrams

    C. Staffing management plan

    D. Responsibility assignment matrix (RAM)

  • Question 265:

    Which technique is used in Perform Quantitative Risk Analysis?

    A. Sensitivity analysis

    B. Probability and impact matrix

    C. Risk data quality assessment

    D. Risk categorization

  • Question 266:

    The product scope description is used to:

    A. Gain stakeholders' support for the project.

    B. Progressively elaborate the characteristics of the product, service, or result.

    C. Describe the project in great detail.

    D. Define the process and criteria for accepting a completed product, service, or result.

  • Question 267:

    What is an objective of the Develop Project Team process?

    A. Feelings of trust and improved cohesiveness

    B. Ground rules for interaction

    C. Enhanced resource availability

    D. Functional managers becoming more involved

  • Question 268:

    Most experienced project managers know that:

    A. every project requires the use of all processes in the PMBOKĀ® Guide.

    B. there is no single way to manage a project.

    C. project management techniques are risk free.

    D. there is only one way to manage projects successfully.

  • Question 269:

    Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

    A. Build vs. buy

    B. Expert judgment

    C. Alternatives identification

    D. Product analysis

  • Question 270:

    What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

    A. Failure modes and effects analysis

    B. Design of experiments

    C. Quality checklist

    D. Risk analysis

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.