While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
A. Utilize the change control process.
B. Crash the schedule to fix the defect.
C. Leave the defect in and work around it.
D. Fast-track the remaining development.
Which action should a project manager take to ensure that the project management plan is effective and current?
A. Conduct periodic project performance reviews.
B. Identify quality project standards.
C. Follow ISO 9000 quality standards.
D. Complete the quality control checklist.
Portfolio Management is management of:
A. a project by dividing the project into more manageable sub-projects.
B. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.
C. all projects undertaken by a company.
D. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.
What is the total float of the critical path?
A. Can be any number
B. Zero or positive
C. Zero or negative
D. Depends on the calendar
The Verify Scope process is primarily concerned with:
A. formalizing acceptance of the completed project deliverables.
B. accuracy of the work deliverables.
C. formalizing approval of the scope statement.
D. accuracy of the work breakdown structure (WBS).
An input of the Control Schedule process is the:
A. resource calendar.
B. activity list.
C. risk management plan.
D. organizational process assets.
An input to the Create WBS process is a:
A. project charter.
B. stakeholder register.
C. project scope statement.
D. requirements traceability matrix.
Which is an example of Administer Procurements?
A. Negotiating the contract
B. Authorizing contractor work
C. Developing the statement of work
D. Establishing evaluation criteria
The scope management plan is a subsidiary of which project document?
A. Schedule management plan
B. Project management plan
C. Quality management plan
D. Resource management plan
Who selects the appropriate processes for a project?
A. Project stakeholders
B. Project sponsor and project stakeholder
C. Project manager and project team
D. Project manager and project sponsor
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.