  • Question 211:

    When is a project finished?

    A. After verbal acceptance of the customer or sponsor

    B. After lessons learned have been documented in contract closure

    C. When the project objectives have been met

    D. After resources have been released

  • Question 212:

    Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

    A. Develop Project Management Plan

    B. Develop Project Charter

    C. Direct and Manage Project Execution

    D. Collect Requirements

  • Question 213:

    Which of the following is an output of the Define Activities process?

    A. Activity list

    B. Project plan

    C. Activity duration estimates

    D. Project schedule

  • Question 214:

    Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

    A. Product

    B. Cost-benefit

    C. Stakeholder

    D. Research

  • Question 215:

    Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

    A. Work breakdown structure

    B. Organizational breakdown structure

    C. Resource breakdown structure

    D. Bill of materials

  • Question 216:

    What is the function of a Project Management Office (PMO)?

    A. To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

    B. To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

    C. To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

    D. To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

  • Question 217:

    Which is a tool or technique used in Define Scope?

    A. Templates, forms, and standards

    B. Change requests

    C. Product analysis

    D. Project assumptions

  • Question 218:

    The integrative nature of project management requires which Process Group to interact with the other Process Groups?

    A. Planning

    B. Executing

    C. Monitoring and Controlling

    D. Project Management

  • Question 219:

    Which type of analysis would be used for the Plan Quality process?

    A. Schedule

    B. Checklist

    C. Assumption

    D. Cost-Benefit

  • Question 220:

    Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

    A. Scope audits

    B. Scope reviews

    C. Quality audits

    D. Control chart

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.