If a project with a CPI of 1.6, what you tell?
A. The project is consuming fewer resources than anticipated
B. The project is using fewer resources than anticipated.
C. The project is falling behind.
D. The project is running ahead of schedule.
You are the project manager and you have created a contract for your customer. The contract must have .
A. Offer and consideration
B. Start date and acceptance of start date
C. Signatures and the stamp of a notary public
D. Signatures of all stakeholders
Which of the following activity is not performed as part of the direct and manage project execution process?
A. Monitor implementation of approved changes
B. Validate deliverables
C. Staff, train, and manage the project team
D. Manage cisks and implement risk responses
If you are project manager for a Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project?
A. Historical information
B. WBS
C. Business plans
D. RBS
You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?
A. Create WBS
B. Vei*
C. Value analysis
D. Control Scope
Which of the following is NOT input of Identify Risks?
A. Project Charter
B. Stakeholder Register
C. Pis'* Management Plan
D. Activity Cost Estimates
Which of the following is NOT an input of Estimate Costs?
A. Earn Value Analysis
B. Scope Baseline
C. P'sk Register
D. Human Resource Plan
You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?
A. Control Schedule
B. Create WBS
C. Sequence Activities
D. Operations
Which process must occur after a project manager has been assigned to the project?
A. Collect Requirements
B. Develop the project charter
C. Develop the project statement of work
D. Develop project closing document
You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?
A. Create WBS
B. Vei*
C. Value analysis
D. Control Scope
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.