  • Question 101:

    The project management plan:

    A. Identifies all the steps and processes that will be used after a project is initiated

    B. Steps needed to complete a project task

    C. Prepared at the beginning and fixed throughout the execution of the project

    D. Includes project charter

  • Question 102:

    You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

    A. Schedule

    B. Assumption

    C. Constraint

    D. Planning process

  • Question 103:

    Which of the following is not part of project scope management?

    A. Verify Scope

    B. Collect Requirements

    C. Create WBS

    D. None of the above

  • Question 104:

    Which of the following plans is not done during the writing of a project plan?

    A. Executive Communication

    B. Risk Management

    C. Quality Management

    D. Scope Statement

  • Question 105:

    Stakeholder influence is greatest at the of the project.

    A. Beginning

    B. Closing

    C. Controlling

    D. Executing

  • Question 106:

    You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years the expected worth of the equipment is $2,000. Using straight-line deprecation, what is the amount that can be written off each year?

    A. $600

    B. $1200

    C. $3000

    D. Zero

  • Question 107:

    Project scope is .

    A. The features and functions that are to be included in a product or service

    B. The work that must NOT be done in order to deliver a product with the specified features and functions

    C. Part 癴tne project charter

    D. Part of sow

  • Question 108:

    Which of the following are parts of project scope management?

    A. Verify Scope

    B. Collect Requirements

    C. Control Scope

    D. Al1 of the above

  • Question 109:

    What are the inputs for Initiation process?

    A. Product description and Strategic plan

    B. Selection criteria

    C. Historical information

    D. Al1 of the above

  • Question 110:

    If a project with a CPI of 1.2, what you tell?

    A. The project is consuming fewer resources than anticipated

    B. The project is using fewer resources than anticipated.

    C. The project is falling behind.

    D. The project is running ahead of schedule.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.