  • Question 71:

    The primary output of the project closing process .

    A. To formalize and distribute all information pertaining to the project closing

    B. Lessons learned

    C. To get customer and sponsor approval

    D. Milestone list

  • Question 72:

    How many communication channels exist in a team of 10 members?

    A. 45

    B. 10

    C. 30

    D. 20

  • Question 73:

    Purchasing insurance is an example of .

    A. Transfer

    B. Acceptances

    C. Mitigation

    D. Contingency

  • Question 74:

    When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?

    A. Parametric estimating

    B. Bottom-up estimating

    C. Top-down estimating

    D. Analogous estimating

  • Question 75:

    You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?

    A. Risk

    B. Assumption

    C. Constraint

    D. Budget

  • Question 76:

    Which process group is for detailed resource assignments and responsibilities?

    A. Human resources management plan

    B. Project charter

    C. Aplan

    D. Project management plan

  • Question 77:

    You are the project manager for a Project. Project is a global project. Some peoples are working from US and some are from India. Client says budget should not cost more than $12 million. Because of the global concerns, the final budget must be in U.S. dollars. This is an example of which of the following?

    A. Internationalization

    B. Budget constraint

    C. Management constraint

    D. Quality constraint

  • Question 78:

    What are the outputs of Initiation process?

    A. Project charter and PM assigned

    B. Constraints

    C. Assumptions

    D. Al1 of the above

  • Question 79:

    Lessons learned session should be held at what point in a project?

    A. At the project conclusion

    B. At key milestones

    C. When risk events occur

    D. When sponsor want

  • Question 80:

    Which is the most risky phase of a project?

    A. Planning

    B. Closing

    C. Execution

    D. Control

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.