Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?
A. Project sponsor and project manager
B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager
How is scheduled variance calculated using the earned value technique?
A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV
The project management processes presented in the PMBOK Guide should:
A. Always be applied uniformly
B. Be selected as appropriate by the sponsor
C. Be selected as appropriate by the project team
D. Be applied based on ISO guidelines.
As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?
A. BAC
B. EAC
C. ETC
D. WBS
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
A. -$700
B. -$200
C. +$200
D. +$500
How is quality control performed?
A. By identifying quality standards that are relevant to the project and determining how to satisfy them.
B. By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed.
C. By ensuring that the entire project team has been adequately trained in quality assurance processes.
D. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance to quality standards.
Who MUST know when a risk event occurs so that a response can be implemented?
A. Customers
B. Project sponsors
C. Project management team
D. Insurance claims department
Which of the following is an example of contract administration?
A. Negotiating the contract
B. Authorizing contractor work
C. Developing the statement of work
D. Establishing evaluation criteria
Scope verification is PRIMARILY concerned with which of the following?
A. Acceptance of the work deliverables.
B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.
During what process is the quality policy determined?
A. Initiating
B. Executing
C. Planning
D. Controlling
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.