  • Question 11:

    Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

    A. 6

    B. 4

    C. 6.3

    D. 6.1

  • Question 12:

    A scope management plan In which of the following scope management processes is the scope management plan prepared?

    A. Initiation

    B. Collect Requirements

    C. Define Scope

    D. Verify Scope

  • Question 13:

    To calculate the late start and late finish dates for a set of tasks , you must do :

    A. An analysis of the critical path

    B. A forwards pass

    C. A backwards pass

    D. a and g

  • Question 14:

    Which is not included in Performance improvements :

    A. Improvements in amount of overtime worked

    B. Improvements in individual skills

    C. Improvements in team behaviours

    D. Improvements in team capabilities

  • Question 15:

    A Trend Analysis is best described as:

    A. Examining project performance over time

    B. Calculating Earned Value

    C. Calculating Cost Variance

    D. Analyzing performance of similar projects over time

  • Question 16:

    In which type of organization, a project manager is in complete control of the project?

    A. Projectized organization

    B. Balanced Matrix organization

    C. Strong Matrix

    D. Weak Matrix organization

  • Question 17:

    In which type of organization, a project manager is in complete control of the project?

    A. Projectized organization

    B. Balanced Matrix organization

    C. Strong Matrix

    D. Weak Matrix organization

  • Question 18:

    Which is the most important element of a Project Management Plan that is useful in the Develop Human Resource Plan process:

    A. Risk Management activities

    B. Activity Resource requirements

    C. Budget Control activities

    D. Quality Assurance activities

  • Question 19:

    Which of the following must be measured regularly to identify variances from the plan.

    A. Stakeholder requirements

    B. Project performance

    C. Control Schedule

    D. Project controls

  • Question 20:

    Identification of Mandatory Dependencies is done during which of the following process:

    A. Sequence Activities

    B. Develop Schedule

    C. Define Activities

    D. Estimate Activity Durations

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.