  • Question 91:

    Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform .

    A. Progressive elaboration

    B. Stake holder's review

    C. p'an project life cycle

    D. Fast backing

  • Question 92:

    In PMBOK, the buyer is to the project team.

    A. Internal

    B. External

    C. Outside

    D. Assigned

  • Question 93:

    Define Scope involves subdividing the major project deliverables into smaller, more manageable components to .

    A. Improve the accuracy of cost, time and resource estimates

    B. Define a baseline for performance measurement and control

    C. Facilitate clear responsibility assignments

    D. Al1 of the above

  • Question 94:

    You are project manager of a project and you are offering an estimate that you know will be changed after the contract is signed is .

    A. Bad practice

    B. Unprofessional practice

    C. Bacl f°r both tne buyer and seller

    D. Al1 of the above

  • Question 95:

    Which document formally authorizes a project?

    A. The project charter

    B. Project scope statement

    C. The P'oject contract

    D. Project closing document

  • Question 96:

    You are working with an organization and you found that one stakeholder not disclosing all of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS that does not include all the tasks necessary to get the project done. What you should do?

    A. Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the project

    B. Confront the other project manager immediately

    C. Mail t0 PMI headquarters

    D. Ignore it

  • Question 97:

    You are the project manager of a project. Your project just went into integration mode. This means that your project .

    A. Has been accepted by the sponsor and the client

    B. Will be closed due to lack of resources

    C. Resources are being assigned to other areas of the business

    D. None of the above

  • Question 98:

    Information should be communicated to .

    A. Everyone in the communication plan

    B. Everyone on the team

    C. Sponsor

    D. Team 'eacl

  • Question 99:

    What are common types of cost-reimbursable contracts?

    A. CPF

    B. CPFF

    C. CPIF

    D. Al1 of the above

  • Question 100:

    Which type of network diagram is also referred to Activity-on-Node (AON) diagrams?

    A. Precedence Diagramming Method (PDM)

    B. Gantt Cnart Diagram (GCD)

    C. Dependency Diagramming Method (DDM)

    D. Arrow Diagramming Method (ADM)

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.