Which is an input to the Scope Verification Process?
A. Performance report
B. Work breakdown structure
C. Requested changes D. Project scope statement
When are deliverables accepted or not accepted?
A. When the project is initiated.
B. As an output of the scope verification process.
C. When the project is closing.
D. In the contract closure process.
Which is a tool used in monitoring and controlling project work?
A. Work performance information
B. Project management information system (PMIS)
C. Activity duration estimates
D. Scheduled network analysis
Which process documents the business needs of a project and the new product, service or other result that is intended to satisfy those requirements?
A. Develop project management plan
B. Develop project charter
C. Develop preliminary project scope statement
D. Scope planning
Which process group typically consumes the bulk of a project's budget?
A. Monitoring and Controlling
B. Executing
C. Planning
D. Initiating
What process determines which risks might affect the project?
A. Qualitative risk analysis
B. Identify Risks
C. Plan Risk Management
D. Quantitative risk analysis
Verification of project deliverables occurs during which process?
A. Develop preliminary project scope statement.
B. Close Project or Phase.
C. Develop project charter.
D. Create WBS.
Information collected on the status of project activities being performed to accomplish the project work is known as what?
A. Project management information system
B. Work performance information
C. Work breakdown structure
D. Variance analysis
To which process is work performance information an input?
A. Contract administration
B. Direction and management of project execution
C. Create WBS
D. Qualitative risk analysis
Which of the following is an output of the Information Distribution Process?
A. Project calendar
B. Communication management plan
C. Requested changes
D. Communication requirement plan
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.