  • Question 241:

    The project team reviews identified risks and the risk response strategy. For one of the risks, the team realizes that the implementation of the risk response would generate another risk. This new risk is which of the following types of risk?

    A. Secondary

    B. Primary

    C. Residual

    D. Tertiary

  • Question 242:

    The project manager decides to conduct a meeting with the team and management after a new risk has been identified. After the meeting, the decision is to allow the risk to occur. This is an example of which type of risk response strategy?

    A. Mitigate

    B. Accept

    C. Avoid

    D. Transfer

  • Question 243:

    What should a project manager do with low-priority risks?

    A. Ignore low-priority risks

    B. Monitor periodically with other low-priority risks

    C. Create a mitigation plan for the low-priority risks

    D. Increase the contingency reserve

  • Question 244:

    Which of the following is a technique for Identify Risks?

    A. Risk categorization

    B. SWOT analysis

    C. Risk register categorization

    D. Risk probability and impact assessment

  • Question 245:

    Which analysis uses beta and triangular distributions as a tool and technique?

    A. Quantitative risk analysis

    B. Qualitative risk analysis

    C. Perform quality assurance

    D. Perform quality control

  • Question 246:

    An Ishikawa or fishbone diagram is used for which of the following?

    A. Identifying causes of risks

    B. Identifying frequency of occurrence of risks

    C. Developing a resource plan

    D. Developing schedule

  • Question 247:

    Which of the following is a strategy for positive risks?

    A. Avoid

    B. Transfer

    C. Accept

    D. Mitigate

  • Question 248:

    What is risk tolerance?

    A. Ability to manage risks

    B. Willingness to accept varying degrees of risks

    C. Ability to mitigate risks

    D. Willingness to develop a risk management plan

  • Question 249:

    Expected Monetary Value (EMV) analysis is commonly used in:

    A. probability distribution.

    B. decision tree diagram.

    C. sensitivity analysis.

    D. modeling and simulation.

  • Question 250:

    Reserve analysis is a tool and technique used in which of the following processes?

    A. Monitor and Control Risks

    B. Qualitative Risk Analysis

    C. Quantitative Risk Analysis

    D. Plan Risk Responses

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.