Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
A. Analogous
B. Parametric
C. Bottom-up
D. Top-down
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work- days. What should be your concern?
A. There is a cost under run.
B. There is a cost overrun.
C. May not meet deadline.
D. The project is 20 days behind schedule.
Which of the following is the correct network diagram for the table?
A. Begin - A - C - D - E - End - B - D
B. Begin - A - B - C - D - E - End
C. Begin - A - B - D - E - End A - C - D
D. Begin - A - C - D - E - End - B - C
Which of the following is a schedule network analysis technique that takes limited resources into account?
A. Network reserve analysis
B. Critical chain method
C. Lead and lag adjustment
D. Critical path method
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
A. The risk of achieving the shortened project time is increased.
B. The critical path will have positive total float.
C. Contingency reserves are released for redeployment by the project manager.
D. Duration buffers are added to maintain a focus on planned activity durations.
Which is a tool or technique used in scope definition?
A. Templates, forms and standards
B. Change requests
C. Stakeholder analysis
D. Project assumptions
What is the total float of the critical path?
A. Can be any number
B. Zero or positive
C. Zero or negative
D. Depends on the calendar
The initial development of a Project Scope Management plan uses which technique?
A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
A. Risk register
B. Risk breakdown structure (RBS)
C. Risk management plan
D. Risk category
During which process would you obtain stakeholders' formal acceptance of the completed project scope?
A. Quality control
B. Scope verification
C. Scope control
D. Close project
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.