provides details about how the project scope may be changed.
A. Control Scope system
B. VeiirV Scope
C. Scope Charter
D. Scope Management plan
Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?
A. Root cause analysis
B. Quality audits
C. Project audits
D. Risk audits
You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn't have the manufacturing capability. This is an example of which selection tool?
A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment
A contract management plan is a subsidiary of what other type of plan?
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan
A contract cannot contain .
A. Illegal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above
Which one of the following comes first in the project plan?
A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
A. Risk identification
B. Qualitative risk analysis
C. Risk management planning
D. Quantitative risk analysis
In which process might you use risk reassessment as a tool and technique?
A. Qualitative risk analysis
B. Risk monitoring and control
C. Monitor and control project work
D. Risk response planning
Which illustrates the connection between work that needs to be done and its project team members?
A. Work breakdown structure
B. Network diagrams
C. Staffing management plan
D. Responsibility matrix
When can pre-assignment of project team members occur?
A. When the project uses capital expenditures.
B. When the required staff can be acquired from outside sources.
C. When the project would be ignored due to travel expenses.
D. When the project is the result of specific people being promised as part of a competitive proposal.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.